Title Page
-
Site conducted
-
Conducted on
-
Prepared by
-
Location
Checklist
Site Cut and Footings
-
Site cut has been completed, providing minimum 400mm clearance between ground and bottom of bearers?
-
Strip footings and pad footings are complete and in correct locations?
-
Pad footings are provided for any required brick piers?
-
If any bored piers required under stump holes, bored piers are poured lower enough to install stumps?
-
Miki pins are done to mark the corners of walls?
-
Footings are exposed and not covered with soil or mud?
-
Site preparation is complete for bricklayers to work safely?
Base Bricks
-
Overall dimensions of base brick walls are correct?
-
If base bricks are single skin brickwork with engaged piers, piers spacing is as per Engineering drawing?
-
Height of internal brick skin/piers are correct and match with bearer bottom level?
-
Opening is provided for stump hole drilling machine to drive in?
-
Access manhole provided?
-
Vents provided in required amount and in correct height?
-
Hoop iron tie downs are provided to tie down bearers?
-
Pockets provided in base bricks for steel columns to sit on strip footings?
Stumps and Subfloor Framing
-
Stump height match with brick/bearer bottom level?
-
Stumps are plumb and straight. Not leaning nor slanted?
-
Any visible cracks in stumps?
-
Stump spacing matches with required bearer span in Engineering drawing?
-
Concrete is not overpoured in stump holes. (Required concrete thickness is about 150mm)?
-
Stump holes are backfilled with dirt and ground within base bricks is levelled and free of debris?
-
Base bricks is completed within the opening left for machine access?
-
Brick piers are built under point load locations if required?
-
Termite barrier is installed on base bricks, piers and stumps?
-
Malthoid is provided under bearers?
-
Bearer size is correct?
-
If any bearers require lapping, correct lap length is provided and additional stumps provided as required?
-
If any joists require lapping, min 300mm lap or blocking at butt joints are provided?
-
Bearers have sufficient end bearing on base bricks?
-
Joist size is correct?
-
Joist spacing is correct?
-
If required, additional joists/joist thickening are provided under load bearing walls?
-
Any required steel beams are installed?
-
If under floor access is difficult in later stage, plumbing rough in is completed?
-
If under floor access is difficult in later stage, ducted heating rough in is completed?
-
If ducted heating is applicable, any heater units to be installed under the floor? If so, sufficient access is available?
-
If under floor access is difficult in later stage, under floor insulation is completed?
Comments / Actions
-
Comments
-
Media
Sign Off
-
Supervisor Signature
-
Date and Time