Site conducted
-
Conducted on
-
Prepared by
-
Location
-
Supervisor and trades name - Particiapted in the tool box meeting
Council local laws
-
Park the Vechile as per council guidelines
-
Open the gate with Gate code and ensure gates not obstructing the foot path.
-
Plan the work as per council wokring hours
-
Ensure Radio volume is not affecting neighbours.
-
Avoid screaming and abusive language.
-
Failure to follow council laws - infringment or back charge will be issued to the sub contractor.
Site Safety
-
Complete Site induction using QR code
-
If you don't complete Construction induction course, please do not enter into the site. Leave the site immediately.
-
Ensure Signed SWMS submitted and risk discussed with Site manager.
-
House keeping to be completed on daily basis. Failure will result in $500 back charge to engage labour to clean the site.
-
Tools must be test and tagged
-
Use the temporary power, temporary toilet, water & Rubbish cage - do not abstruct the access
-
Stack the material without causing tripping hazard and driveway is clear and accessible.
-
Ensure Fall protection installed while you are planning to work from height. Please raise alarm to Site manager or Senior project manager or Contract Admin or Construction manager for the support required.
-
Do not alter fall protection system. Please contact Site manager for the support required.
Action items
-
-
Site manager : Action item and time line to complet the task.
-
Sub contractors: Action item and Time line to complete the task