PRE -ARRIVAL PREPARATIONS.

  • 1/CONTRACTOR TO GIVE WITTEN NOTIFICATION TO THE ERECTOR THAT: The concrete in the footings, piers and walls and/the mortar has attained sufficient strength to support the loads imposed during steel erection.

  • 2/ Prior to the erection of any column, written notification of any repaired ,replaced, or field-modified anchor bolts and certification that those modification were done with the approval of the structural engineer of record.

  • 3/ Prior to steel being placed all other construction trades and processes will be barred from conducting work beneath the steel erection activities unless overhead protection is provided.?

  • 4/ Will arrangements for the steel erector to leave the fall protection that they erected in place for the other trades to use?

  • 5/ Are there adequate roads into and through the site for the safe delivery and movement of derricks, cranes,trucks and other necessary equipment?

  • 6/ Is there sufficient access room for separate vehicular and pedestrian traffic?

  • 7/ Is the site prepared in such a way that it is firm, properly graded, drained and readily accessible to the work area?

  • 8/ Is there adequate space for the safe storage of materials and the safe operation of the erectors equipment?

  • 9/ Will the material handling procedures be pre-planned in such a way that no employee will be required to work beneath a suspended load?

  • 10/ Steel erector will provide the CONTRACTOR with a site-specific erection plan for this project.

HOISTING AND RIGGING (1926.753)

  • 1/. Crane operators license must be current to operate equipment. COPY to the contracor

  • 2/. Has the crane had an annual inspections and did it pass the inspection within the past year?

  • 3/. Does the operator conduct crane inspections of machinery and moving parts before each use?

  • 4/. Swing radius of crane fully protected to prevent an employee from being struck or crushed?

  • 5/. Fire extinguisher rated 5 BC or above at the operators station?

  • 6/. The crane operator has direct control over the safety of the load, They have the responsibility to stop and to refuse to handle the load until it is made safe?

  • 7/. Does Fully qualified rigger inspect the rigging prior to the commencement of each shift?

  • 8/. Safety latches on hooks must be operable

  • 9/. Only employees engaged in steel connection or hooking or unhooking of the load permitted to be beneath the suspended load.

  • 10/. Will loads be properly rigged/carried when swung over the heads of authorised workers who can work beneath them?

STRUCTURAL STEEL ASSEMBLY (1926.754)

  • 1/ Fully planked or deck floor or nets must be installed and maintained within two stories or 30 feet, whichever is less, directly under erection work.

  • 2/ Plumbing -up equipment must be properly installed before the structure is loaded with construction material.

  • 3/ Metal decking must be securedagaist displacement before the end of shift.

  • 4/ Floor openings must be covered and mark or protected by guard rails or nets

  • 5/ Metal decking must be secured upon placement

COLUMN ANCHORAGE (1926.755)

  • 1/ Columns will be anchored be a minimum of 4 anchor bolts.

  • 2/ Competent person must determine whether guying or bracing is required.

FALL PROTECTION (1926.760)

  • 1/ Will perimeter safety cables be installed at the final interior & exterior perimeters of the floor & roof before the metal decking is installed?

  • 2/ All steel erection employees must have and use fall protection when 6'-0 feet and above.

  • 3/ Have all connectors been trained in accordance with 1926.761?

  • 4/ Is the Controlled Decking Zone restricted to employees engaged in the leading edge work?

  • 5/ Will the boundaries of the CDZ and within 90'-0 feet of the leading edge be clearly marked?

  • 6/ Have all the employees who will be working within the CDZ been trained in accordance with 1926.761?

  • 7/ No final deck attachments are to be made within the CDZ.

  • 10/ A good accessible ladder installation must be installed to upper and lower floor.

TRAINING (1926.761)

  • 1/ Steel Erector must provide to CONTRACTOR. documentation that all their employees have been trained on FALL HAZARDS.

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.