Title Page
-
Conducted on
-
Prepared by
-
Location
TIMBER FLOOR STRUCTURE
-
Are large span floor joists installed as per manufacturer's specifications/layouts?
-
Have the load-bearing points been set up for girder trusses etc? (where applicable)
-
Has the sheet flooring been installed as per manufacturer's recommendation?
WALL FRAME
-
Check room sizes & ceiling heights as per plans & details
-
Check walls for plumb, square, straight & level (must not exceed 4mm in 2m length)
-
Check bottom plate is sitting securely on the floor surface (if not refer to Engineer to provide rectification detail)
-
Check all bracing and tie downs are installed as required and wind rating requirements complied with
-
Check noggins are installed for all bathroom accessories- by wall manufacturer
-
Check all stud to plate connections are securely fixed and tightly fitted together
-
Ensure wall intersection blocks are installed correctly for lock up carpenter to connect when straightening walls
-
Check all wastes are located as per plan. Floor joists are designed & installed to work in with floor wastes and that there are no clashes
-
Check all beams to openings and spans are installed and fixed correctly as per details
-
Check all doors and openings are correct size and correctly located as per IFC plans
WINDOW INSTALLATION
-
Check all windows are plumb, square & installed to manufacturer's requirements (Note: must be packed to manufacturer's specification.)
-
Check all window reveals are undamaged
-
Ensure all window frames are free of damage or defects
-
Are all window flashings installed?
CEILING AND ROOF FRAME
-
Check that all roof trusses have been installed in accordance with the Truss Manufacturer's design and layout
-
Check that all girder trusses are correctly supported i.e. point loading has been provided
-
Check that stairwell walls are correct i.e. raking walls are correct height. No timber members protruding into stairwell
-
Check that all connections, bracing and tie downs have been installed in accordance with manufacturer's recommendations
-
Ensure that secondary plates have been installed to load bearing walls
-
Non-load bearing walls are to be free of bottom of truss chord by the thickness of the secondary plate
-
Have any trusses been damaged from original condition whilst placing in final position? If yes, consult with manufacturer for correct rectification procedure)
-
Have trusses been designed to cope with any known loads? i.e. air conditioning, solar heating panels etc
-
Are trusses installed within installation tolerances?
-
1. Plumb -apex <50mm or standard/200 out of vertical
-
2. Plumb -all sections of truss < 50mm or height/50 out of vertical
-
3. Bow -all chord bows <50mm or cord length/200
-
Are all multiple trusses correctly secured together as per manufacturer's details?
-
Are walling plates securely fixed to wall and truss as designed?
-
Are parapets as per plan? Height etc? Do they allow adequate upstand for flashings?
-
PERMANENT BRACING
-
Are top chord temporary ties no greater than 3m spacing?
-
Are bottom chord temporary ties no greater than 4m spacing?
-
Is the speed bracing configuration correct?
-
Is the apex bracing installed correctly?
-
Is the speed bracing fixing to each truss top chord correct?
-
Has the speed bracing been correctly fixed?
-
Has all bracing ply been installed as required?
-
Is all bracing installed as per Engineers requirements? (refer to engineers IFC documentation)
TRUSS CONNECTION DETAILS
-
Have all connections been secured in accordance with guideline requirements?
-
Have internal walls been secured to trusses and internal wall brackets?
-
Check all internal wall brackets for correct fixing
-
Ensure all connection guidelines of truss installations are met
-
PRE-ROOF COVER
-
Check correct eave overhang on truss tail for fascia/barge and lining as required
-
Check all box gutter boarding is installed to required standards & provision is made for sumps and overflows
-
Check all roof cover battens have been installed correctly to meet roof truss design requirements and roof covering material being installed
-
Has man hole been framed/trimmed as per plan? (If applicable)
-
Has frame been inspected and passed by Building Surveyor? Y / N (please circle one)
-
Subcontractor Representative:
-
Date:
-
Signature: