Title Page

  • Conducted on

  • Prepared by

  • Location

TIMBER FLOOR STRUCTURE

  • Are large span floor joists installed as per manufacturer's specifications/layouts?

  • Have the load-bearing points been set up for girder trusses etc? (where applicable)

  • Has the sheet flooring been installed as per manufacturer's recommendation?

WALL FRAME

  • Check room sizes & ceiling heights as per plans & details

  • Check walls for plumb, square, straight & level (must not exceed 4mm in 2m length)

  • Check bottom plate is sitting securely on the floor surface (if not refer to Engineer to provide rectification detail)

  • Check all bracing and tie downs are installed as required and wind rating requirements complied with

  • Check noggins are installed for all bathroom accessories- by wall manufacturer

  • Check all stud to plate connections are securely fixed and tightly fitted together

  • Ensure wall intersection blocks are installed correctly for lock up carpenter to connect when straightening walls

  • Check all wastes are located as per plan. Floor joists are designed & installed to work in with floor wastes and that there are no clashes

  • Check all beams to openings and spans are installed and fixed correctly as per details

  • Check all doors and openings are correct size and correctly located as per IFC plans

WINDOW INSTALLATION

  • Check all windows are plumb, square & installed to manufacturer's requirements (Note: must be packed to manufacturer's specification.)

  • Check all window reveals are undamaged

  • Ensure all window frames are free of damage or defects

  • Are all window flashings installed?

CEILING AND ROOF FRAME

  • Check that all roof trusses have been installed in accordance with the Truss Manufacturer's design and layout

  • Check that all girder trusses are correctly supported i.e. point loading has been provided

  • Check that stairwell walls are correct i.e. raking walls are correct height. No timber members protruding into stairwell

  • Check that all connections, bracing and tie downs have been installed in accordance with manufacturer's recommendations

  • Ensure that secondary plates have been installed to load bearing walls

  • Non-load bearing walls are to be free of bottom of truss chord by the thickness of the secondary plate

  • Have any trusses been damaged from original condition whilst placing in final position? If yes, consult with manufacturer for correct rectification procedure)

  • Have trusses been designed to cope with any known loads? i.e. air conditioning, solar heating panels etc

  • Are trusses installed within installation tolerances?

  • 1. Plumb -apex <50mm or standard/200 out of vertical

  • 2. Plumb -all sections of truss < 50mm or height/50 out of vertical

  • 3. Bow -all chord bows <50mm or cord length/200

  • Are all multiple trusses correctly secured together as per manufacturer's details?

  • Are walling plates securely fixed to wall and truss as designed?

  • Are parapets as per plan? Height etc? Do they allow adequate upstand for flashings?

  • PERMANENT BRACING

  • Are top chord temporary ties no greater than 3m spacing?

  • Are bottom chord temporary ties no greater than 4m spacing?

  • Is the speed bracing configuration correct?

  • Is the apex bracing installed correctly?

  • Is the speed bracing fixing to each truss top chord correct?

  • Has the speed bracing been correctly fixed?

  • Has all bracing ply been installed as required?

  • Is all bracing installed as per Engineers requirements? (refer to engineers IFC documentation)

TRUSS CONNECTION DETAILS

  • Have all connections been secured in accordance with guideline requirements?

  • Have internal walls been secured to trusses and internal wall brackets?

  • Check all internal wall brackets for correct fixing

  • Ensure all connection guidelines of truss installations are met

  • PRE-ROOF COVER

  • Check correct eave overhang on truss tail for fascia/barge and lining as required

  • Check all box gutter boarding is installed to required standards & provision is made for sumps and overflows

  • Check all roof cover battens have been installed correctly to meet roof truss design requirements and roof covering material being installed

  • Has man hole been framed/trimmed as per plan? (If applicable)

  • Has frame been inspected and passed by Building Surveyor? Y / N (please circle one)

  • Subcontractor Representative:

  • Date:

  • Signature:

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.