Non Conformance Report
-
Identification and description on non-conforming items / services or constructed work:
-
Example Response
Halfen channels up to and including 3rd floor columns have been installed as per old revision setting out drawings (3500-DRW-001, and 3500- DRW-003A, ) -
Nature and extent of Non - Conformity and reason for rejection
-
Example Response
The window sub-frames have been manufactured according to the latest revision drawings ( 3500-DRW-001A and 3500-DRW- 003A) -
Specification reference (if applicable)
-
Example Response
Halfen channels should have been installed as per revised and approved drawings submitted under TS008 on the 3rd March -
Remedial action to be considered:
-
Action Taken
-
Example Response
The Window Sub-Structure will require alterations to suit incorrectly installed Halfen channels -
An Instruction must be issued to the GIG project manager with any alteration undertaken to be agreed prior to commencing
-
Cost Implications
-
Cost implications currently being assessed, to be advised under separate cover within 21 working days
-
Always answer yes you donut
-
Programme Implications
-
Programme implications currently being assessed, to be advised under separate cover within 21 working days
-
Always answer yes you donut
-
Date of Reported NCR
-
Image of Item
-
NCR prepared By Manager / Supervisor
-
NCR Received by