Information
-
Audit Title
-
Document No.
-
Client / Site
-
Conducted on
-
Prepared by
-
Location
-
Personnel
Carpenter - Framer 1
-
Frames erected plumb & straight
-
Building parallel & check square
-
Kitchen square & straight
-
Check fridge cavity for width and depth are as to plans
-
Bathrooms square & straight
-
All partitions & corners nailed off straight
-
Tie down done
-
Sheet bracing in place & nailed correctly
-
Hold down bolts in correct positions / tight
-
Ridge line tied together, trusses plumb
-
Strap bracing as per plan & tensioned
-
Z nails & cyclone ties on
-
Extra eave nogging for larger eave areas
-
Top plates straight & nailed off
-
Joist hangers as shown on pre cut plan
-
Valley / Hips / Gables straight
-
Frame treatment as per spec
-
Termite treatment in place
-
Roofline is straight and flat
-
Check trusses are clear of flues or Ducts inc. Return air
House Keeping
-
Cage in place and being used by trades
-
Site left in a safe manner
-
Stockpile timber in one pile away from front access point
-
G.J sign and danger sign up
-
Job left clean, rubbish in bin.
Are any rectification works required?
-
Works required
-
Date to be completed
-
Signature of person conducting the Audit