Information
-
Site Address
-
Job Ref No
-
Engineer Name
-
Employee / Sub contractor
-
Company name
-
Work Activity
-
Date of Inspection
-
Inspected by
-
Document No.
First Impressions - Engineer & Appearance
-
Is vehicle parked correctly and at a suitable location?
-
Is vehicle clean outside?
-
Is vehicle tidy inside?
-
First Aid kit on vehicle?
-
Is it within expiry date?
-
Engineer must replace items or kit and ensure adequate First Aid kit is carried on vehicle
-
Is engineer wearing Correct uniform?
-
Is it clean and well presented?
-
Is company I.D being worn?
-
Is engineer wearing a Hi-Vis vest?
-
Is engineer wearing safety boots?
-
Is the site in a tidy condition?
Health & Safety
-
Has site induction and/or sign in taken place?
-
Copy of Risk Assessment and method statement present?
-
Is it suitable and sufficient, adequately controlling hazards to an acceptable level?
-
Are contractors working to the requirements of the permit issued?
-
For a site to be notifiable under CDM 2015 it must meet the following requirements:
- last longer than 30 working days and have more than 20 workers working simultaneously at any one time or;
- exceeds 500'person days -
Is the site notifiable under CDM 2015?
-
Have all operatives signed in?
-
Are welfare facilities adequate?
-
Is the Construction Phase Plan adequate for activities?
-
Has the Construction Phase Plan been reviewed and recorded?
-
Are copies of inductions and certificates of competences held on site?
-
Copy of F10 valid and displayed?
Environmental
-
Are dust creating activities being adequately controlled?
-
Are noise creating activities being adequately controlled?
-
Is any COSHH items being adequately controlled?
-
Is any hazardous waste being created?
-
Are the facilities for disposal adequate?
Working at Heights
-
Is MEWP being used?
-
Has full handover of plant been carried out and sheet present?
-
Is Operators Manual present?
-
Has Plant inspection been carried out?
-
Is Fall Arrest system being used?
-
Is correct PPE Being worn?
-
Is a scaffold tower being used?
-
Is it erected correctly?
-
Has the engineer received full training how to use / erect correctly?
-
Are Step Ladders being used?
-
Are they set up on Level Ground?
-
Advise engineer of the risks associated with non level ground and corrective actions to be carried out
-
Are steps in safe condition and free from damage?
-
Are they being used safely and in the correct manner?
-
Are they tagged and in date?
-
Were Leaning Ladders being used at time of visit?
-
Ladders in good condition and free from damage?
-
Ladders tied in with ratchet straps and eyebolts?
-
Rope on Ladder?
-
Engineer wearing Harness with cows tail & rope grab?
-
Ladder stand off (micro-lite) used?
-
Ladder stabiliser used?
-
Ladder leveller used?
-
Ladder at correct angle? (1 in 4)
-
Could 3 points of contact be maintained whilst ascending & descending?
-
Hard hat worn whilst on ladder?
-
Any comments or corrective actions taken place
-
Photos of Ladder setup (if required)
-
Is there evidence of WAH kit used, I.E-eyebolts or drill holes, kit left out etc?
-
Photos of WAH evidence
-
Is Fixed Scaffold being used?
-
Has Scaffold been inspected within the last 7 days?
-
Work is to cease immediately pending Scaffold Tag inspection and if applicable the client is to be contacted.
-
Do engineers have permission to access scaffold?
-
Permission from client is to be sought immediately.
Working at Heights - Roof work
-
Was Roof Access required?
-
Pitched roof or Flat roof?
-
Does the flat roof have edge protection?
-
Was the engineer safe and risk of falls minimised?
-
Was a 2m exclusion zone set up around the roof edge?
-
Were suitable Anchor points available?
-
Was a man anchor required? (Dead mans anchor)
-
Details
-
Was the man anchor set up correctly with full fall restraint system in place?
-
Eyebolts drilled/Anchor points used and fall restraint system set up correctly?
-
Was Roof ladder set up correctly? (Strapped to triples etc)
-
Any comments or corrective actions taken place
-
Photos of roof areas, set up if required
Manual Handling
-
Have mechanical means been used?
-
Are safe lifting techniques being observed?
Electricity
-
Has electrical isolation taken place?
Equipment
-
Is electrical equipment in good condition?
-
Remove from service
-
Is any work equipment safe and free from wear and tear??
-
State which pieces and remove from service
Personal Protective Equipment (PPE)
-
Eye protection used when drilling?
-
Ear protection used? (Defenders or plugs)
-
Hand protection worn when required?
-
Dust masks worn when required?
-
Overshoes worn? (If applicable)
-
Where PPE is not required is it stored appropriately?
-
Explain to engineer the importance of correct storage of PPE
Signage & Barriers
-
Were road or pathway cordons set up?
-
Should road or pathway cordons have been implemented to protect the public etc?
-
Details and corrective actions taken place
-
Photos of areas that should have been cordoned off
-
Correct use of Cones?
-
Correct use of Barrier tape?
-
Correct use of signage? (Cable in progress etc)
-
Photos of cordons put in place
Asbestos
-
Has asbestos been identified on site?
-
Have asbestos precautions been followed?
-
Work must be stopped immediately, H&S department and line manager contacted and the asbestos register consulted.
Vibration
-
Is risk from exposure from vibration being adequately controlled?
Lighting
-
Is lighting suitable for task?
-
Ensure task has sufficient lighting before continuing
Completion
-
Has a full H&S kit inspection been carried out within the last 6 months?
-
A full Health & Safety kit inspection is to be carried out by a competent person. H & S department to be contacted
-
Date of last Kit Inspection
-
Document number
-
Any comments
-
Engineer Training required?
-
Details of training to be given
-
Is escalation / further investigation required?
-
Details
-
Engineer 1
-
Engineer 2
-
Senior Supervisor or H&S manager