Title Page
-
Site conducted
-
Audit Title
-
Project Name
-
Conducted on
-
Prepared by
-
Location
-
Instructions
-------------------
1. Answer "Checked" or "Hold" for the questions below, then identify the personnel who conducted the checking.
2. Add photos and notes by clicking on the paperclip icon.
3. To add a Corrective Measure click on the paperclip icon, then "Add Action", provide a description, assign to a member, set priority and due date.
4. Complete audit by providing digital signature.
5. Share your report by exporting as PDF, Word, Excel or Web Link
Fire barriers to cavity of SFS to Gas Flues and extract vents
-
Main Contractor:
-
Project Number:
-
Issued to:
-
QA Sheet No:
-
Elevation:
-
Level:
-
Comments:
Installation
-
Position of vertical fire barrier correct as per A2o drawing
-
Personnel
- Installer
- A2O
-
Install bracket to cement board/ stud to site under the fire barrier to the correct level
-
Personnel
- Installer
- A2O
-
Check sidewise brackets are secured at the correct centres and length (Brackets 75% embedment into barrier)
-
Personnel
- Installer
- A2O
-
Horizontal fire barrier (CW FS 120) fitted with the correct compression (10mm)
-
Personnel
- Installer
- A2O
-
Fit continuous 120 x 75 x 3mm angle to the bracket
-
Personnel
- Installer
- A2O
-
Apply cortex A2 membrane to cement board and face of continuous angle
-
Personnel
- Installer
- A2O
-
Dress Tyvek over EPDM
-
Personnel
- Installer
- A2O
-
Silver foil tape applied across all joints
-
Personnel
- Installer
- A2O
Completion
-
Installer Signature:
-
A2O Signature:
-
Client Signature: