Title Page
-
Site conducted
-
Project Name
-
Inspection Date and TIme
-
Name of project team management to accompany HSEQ Department on audit.
-
Audit No.
-
Location
-
This report records the findings of the HSEQ Audit/Inspection of the above site.<br><br>NB: Have all action items from the previous audit been closed out?
-
Was the weekly HSEQ submission form recieved for the previous week?
-
Was the project statistics form recieved for the previous week?
SITE AUDIT REPORT
SAFETY MONITORING
-
1. Site Safety Competent & C-19 Compliance Officer/s Person clearly defined for site?
-
2. P.P.E. being used correctly and compliant with the manufacturers usage directions? PPE locked in a secure location, issuing forms completed by issuer?
-
3. Have all employees / sub contractors completed the Kilwex Ltd, Client and or PSCS site specific inductions? Competency of operators checked by site supervision prior to commencement of works?
-
4. Have all employees/sub contractors been briefed, read and signed the Company Safety Statement and or CSHP?
-
5. Have all employees/sub contractors been briefed on the project RAMS? Have they read and signed acceptance thereof?
-
6. Have all sub contractors submitted training certificates been reviewed and uploaded to Union Square?
-
7. Copies of all RAMS available in the work area, or in a file for ease of access by all project members?
-
8. Is the Kilwex Ltd HSE File being maintained weekly by site supervision, employees training records, registers, GA1’s, GA2’s & GA3’s,Inspections, etc. and uploaded to Union Square?
-
9. Are all required safety signs(Warning, Prohibitory & Information) prominently displayed on sites and offices?
-
10. Are Client identification cards/badges visible and names on hard hats. (If Applicable)?
-
11. Are all fire extinguishers(Site & Vehicle) inspected with the past six months and in place in all designated locations?
-
12. Check records of permit to work systems, completed, authorised by Kilwex Ltd and Client/PSCS and closed out at the end of each day/shift?
-
13. Is a daily white board meeting taking place on site?
-
14. Kilwex Ltd employees & Subcontractors training up to date, dipstick testing completed, and training verified?
-
15. Two fire extinguishers(CO² & Powder) and fire blanket in place for all Hot Works?
-
16. Kilwex Ltd and subcontractor’s housekeeping/storage maintained to high standard?
-
17. 'Clean as you go' Policy' being adhered to?
-
18. Emergency plans in place and relevant drills completed monthly?
-
19. AF3 completed for all excavations?
-
20. All excavation shoring, battering and edge protection in place?
-
21. All Excavations have barriers & warning signage in place to prevent unauthorised entry?
-
22. Do all excavations have a safe method of access & egress?
-
23. Onsite traffic management plan in place to ensure safe segregation of pedestrian and site vehicles?
-
24. Have exclusion zones been created within the project zone & the relevant signage attached?
-
25. All OPE's, Manholes, etc. covered and protected sufficiently? With a load or non load bearing sign attached, where applicable?
-
26. Daily SPA's completed by all crews?
-
27. Fixed scaffolding inspected within the last 7 days and signed off by a CSCS Scaffolder, handover and inspection sheets uploaded to U.S.?
-
28. All Straight & Access ladders into excavations in good working order and tag signed off within the last 7 days?
-
29. All Mobile Aluminum Access Towers erected as per manufacturers instructions by a CSCS competent person and tag signed off within the last 7 days?
-
30. Have all Slip, Trip and Fall hazards been identified and mitigated?
-
31. Have all areas where water accumulation occurs been pumped out?
-
32. All rebar capped?
-
33. Access & Egress to Client/Site emergency exits and or routes maintained and clear?
-
34. All Site Perimeter fencing and gates secured?
ENVIRONMENTAL MONITORING
-
1. Are all hazardous substances on site containers marked as per CLP Regulations and are containers maintained and stored correctly?
-
2. Is the Hazardous storage unit indicated marked with approved Kilwex Ltd Signage?
-
3. Is the hazardous substance SDS register up to date and? Have all SDS's been uploaded to Union Square?
-
4. Spill kits strategically placed across the site and within all Site vehicles/Plant where applicable?
-
5. Colour coded recycling bins placed in designated locations with signage attached to identify each waste stream?
-
7. Is all hazardous & Inert waste been disposed of correctly and recorded within the waste register and written transfer notes uploaded to U.S.?
-
8. Have there been any hazardous spills/leaks or evidence thereof from any plant and equipment, fuel drums etc., or other spills? If so was a Kilwex Ltd. Spill report completed on IMS_E060?
-
9. Has of the Appointed waste removal company's license been uploaded to Union Square?
-
10. Welfare facilities free from water leaks?
-
11. Evidence of spill mats being used during refueling activities?
HEALTH & WELFARE MONITORING
-
1. All employees & subcontractors observing COVID 19 safety protocols as per HSE/WHO/CIF Guidance?
-
2. Are Kilwex Ltd activities that generate dust or fumes controlled to eliminate or reduce the risk to exposure?
-
3. RPE worn by all Kilwex Ltd and subcontractors as required?
-
4. Are there clearly visible and legible signs indicating that the noise level in the area is likely to exceed 85dBA?
-
5. Canteens, drying, toilets adequate with heat, lighting, bins in areas and maintained to acceptable standard and complying with HSE C-19 guidelines?
-
6. Is drinking water freely available across the site?
-
7. Adequate number of First Aid Responders and first aid equipment stocks replenished?
-
8. Health Hazards - Asbestos, Dust & Silica, Noise, Vibration, Biological, Stress and Fatigue managed across the site?
QUALITY MONITORING
-
1. Has the project Quality plan in place and uploaded to U.S.?
-
2. Are scheduled Quality audits being completed and uploaded to U.S.?
-
3. Equipment requiring calibration – calibration tag, sticker and certificate is current?
-
4. Appropriate hand/Insulated tools used by all Kilwex Ltd and subcontractors?
-
5. Materials/equipment is stored in clean/ dry location and not stored in the same containers?
-
6. Quarantine area is set up, verify non-conformance reports issued for any materials/Equipment?
-
7. All Kilwex Ltd site plant/vehicles plant GA2's completed manually or via Assetminder daily?
SIGN OFF
-
EHS DEPARTMENT (Name and Signature)