Title Page

  • Site conducted

  • Audit Title

  • Project Name

  • Conducted on

  • Prepared by

  • Location
  • Instructions
    -------------------
    1. Answer "Checked" or "Hold" for the questions below, then identify the personnel who conducted the checking.
    2. Add photos and notes by clicking on the paperclip icon.
    3. To add a Corrective Measure click on the paperclip icon, then "Add Action", provide a description, assign to a member, set priority and due date.
    4. Complete audit by providing digital signature.
    5. Share your report by exporting as PDF, Word, Excel or Web Link

Y Wall Board

  • Main Contractor:

  • Project Number:

  • Issued to:

  • QA Sheet No:

  • Elevation:

  • Level:

  • Comments:

STRUCTURE

  • SFS area + QA complete.

  • Personnel

Y Wall Board

  • Confirm 12mm Y wall board is being used as per ICS drawings.

  • Personnel

  • Y wall board fixings to SFS to be at maximum 600mm centres horizontally and 300mm centres vertically.

  • Personnel

  • Joints on boards to be sealed using RCM UV DAFA tape.

  • Personnel

  • Movement joints left between boards at slab level.

  • Personnel

Additional / bespoke items

  • Additional / bespoke items

Completion

  • Installer Signature:

  • ICS and Signature:

  • Client Signature:

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.