Title Page
-
Site conducted
-
Audit Title
-
Project Name
-
Conducted on
-
Prepared by
-
Location
-
Instructions
-------------------
1. Answer "Checked" or "Hold" for the questions below, then identify the personnel who conducted the checking.
2. Add photos and notes by clicking on the paperclip icon.
3. To add a Corrective Measure click on the paperclip icon, then "Add Action", provide a description, assign to a member, set priority and due date.
4. Complete audit by providing digital signature.
5. Share your report by exporting as PDF, Word, Excel or Web Link
Horizontal Siderise Firebarrier
-
Main Contractor:
-
Project Number:
-
Issued to:
-
QA Sheet No:
-
Elevation:
-
Level:
-
Comments:
Siderise fire barrier materials
-
Fire barrier schedule is available<br>within the site documentation
-
Personnel
- Installer
- A2O
-
Fire barrier materials have been<br>checked on delivery to site to be<br>correct type and specification in<br>accordance with the ICS fire barrier<br>schedules.
-
Personnel
-
Fire barrier materials have been<br>stored on site in an appropriate<br>manned in accordance with<br>manufacturers recommendation.<br>"Keep material in original packaging<br>until it is to be used. Store material<br>to protect against<br>damage including the weather"
-
Personnel
-
All fire barrier brackets, fixings and<br>tape has been delivered to site and<br>checked that they are in accordance<br>with the ICS fire barrier schedule<br>and manufacturers specification.
-
Personnel
Pre-installation
-
A site meeting with fire barrier<br>supplier [Siderise] arranged and<br>carried out in advance of installation<br>works commencing. To include any<br>training that may be required.
-
Personnel
- Installer
- A2O
-
ICS Fire barrier construction<br>drawing are on site within the ICS<br>drawing file.
-
Personnel
- Installer
- A2O
-
All installation operatives have been<br>briefed on the specific installation of<br>the fire barriers to be installed, in<br>accordance with manufacturers<br>recommendation
-
Personnel
Fire barrier installation
-
Ensure that horizontal barriers are<br>installed after vertical barriers.
-
Personnel
- Installer
- A2O
-
Check fire barrier locations are in<br>accordance with ICS fire barrier<br>setting out construction drawings.
-
Personnel
- Installer
- A2O
-
At each fire barrier location, check<br>that thickness of fire barrier is in<br>accordance with cavity void and<br>allow a 50mm air flow gap between<br>the fire barrier front edge and the<br>rear face of the cladding panel. in<br>accordance with the manufacturers<br>specification.
-
Personnel
- Installer
- A2O
-
If the horizontal fire barrier to be<br>installed requires to be cut to size,<br>make sure that you cut the rear<br>edge of the barrier in accordance<br>with manufacturers specification.
-
Personnel
- Installer
- A2O
-
Manually fold RH installation<br>brackets 90 degrees at a point to<br>allow the correct embedment into<br>the fire barrier. This needs to be<br>long enough to allow the split end of<br>the bracket to protrude from the<br>barrier front face.
-
Personnel
- Installer
- A2O
-
RH Bracket fixings are fixed at<br>400mm centres with non<br>combustible fixings [no plastic or<br>rubber washers]. Ensure fixings are<br>as per ICS and manufacturers<br>specification. [3 x brackets per<br>1200m barrier length] no
-
Personnel
- Installer
- A2O
-
Ensure that the fire barrier is tightly<br>abutted to the barriers to each side<br>and seal the joints with RFT 120 x 45<br>foil tape.
-
Personnel
- Installer
- A2O
-
Arrange inspection by Siderise before commencing with any further cladding finishes.
-
On completion of inspection, cavity<br>fire barriers are to be signed off by a<br>Siderise approved qualified person.
Completion
-
Installer Signature:
-
ICS Signature:
-
Client Signature: