Information

  • Job Number:

  • Site Location

  • Client Name

  • Conducted on

  • Inspected by

  • Site Supervisor

  • Location
  • List Irwin Electrical personnel and subcontractors on site:

Site Folder and Paperwork

  • Have all engineers been inducted to site?

  • Have all engineers and personnel signed into site?

  • Is there a method statement and risk assessment available on site corresponding to the works?

  • Has the Method Statement been read and understood by all engineers?

  • Are Emergency / Evacuation plans clear and recorded

  • Are CSR/CSCS cards and training records available?

  • Has daily ladder register been completed?

  • Are COSHH assessments available or hazardous substances on site?

  • Are all subcontractors cleared and training information provided?

  • Is a permit to works in place?

  • Take photo of permit to work

Working Area

  • Is there adequate access and egress throughout workplace?

  • Is there good housekeeping & have materials been stored correctly?

  • Is there adequate safety signage work segregation in place

  • Are adequate emergency procedures in place?

  • Is waste segregation occurring on site?

Means of Access

  • Are ladders or steps being used?

  • Are Ladders / Steps numbered and in good condition?

  • Is the operative keeping 3 points of contact with the ladder / Steps?

  • Are mobile towers being used on site?

  • Has Mobile Tower Scaffold been erected correctly with Tags in place?

  • Was the person erecting the scaffold trained to do so? (PASMA)

  • Take photo of scaffold / Scaff tag

  • Are MEWPs (scissor lift/Cherry pickers) being used on site

  • Is the operative IPAF trained to the correct level

  • Is there a maintenance record available for MEWP

  • is a harness being used by the trained operator?

  • Insert harness plant Number

  • Has a Rescue plan been completed

  • Insert photo of rescue plan in place

Plant and Equipment

  • Is required PPE being worn as per the risk assessment?

  • Power tools in good general condition?

  • Has a Portable Appliance Test (PAT) been carried out in the last 6 Months?

  • Time and Date of PAT

  • Attach photo of sample PAT sticker

  • Are tools and equipment operated in a safe manner and in good condition?

  • Do engineers have Lock Out Tag Out kit?

  • Have test meters been calibrated within the last 3 Months?

  • Have all risks been adequately controlled by the risk assessment?

  • Is there a company vehicle on site?

  • Enter Vehicle Registration

  • Is first aid kit available in Vehicle?

  • Is the vehicle well stocked?

  • Is the vehicles van file available?

  • Is the vehicle in good condition and working order?

Closing Out

  • Have the findings of the inspection been relayed to site supervisor?

  • Signature of person conducting audit

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.