  • Site Inspected
  • Inspected on

  • Prepared by

  • Location (Plot number, Trafo number where the trench is been dug)
  • Are the location of the trenches according to the design?

  • Has the trench been dug to the correct depth and width according to the design? (ensure photos are being taken with evidence of the measurements)

  • Do all cables have the correct spacing according to the design?

  • Have the trench been bedded with sand? (Minimum of 200 mm space to the clay in every angle)

  • Has the correct cable been installed?

  • Do all the cables in the trench have the correct spacing according to the design?

  • Do all cables in the trench have the correct bend radius?

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.