Titelpagina

  • Site Inspected

  • Inspected on

  • Carried out by

  • Location (Plot number and Trafo number)
  • Are the location of the trenches dug according to the design?

  • Has the trench been dug to the correct depth and width in accordance with the design? (ensure photo is showing the evidence of the measurement being taken)

  • Has the correct cable type been used?

  • Has warning tape been installed over the cables?

  • Is the correct amount of sand been used in the trench? (Cables should have a minimum of 200mm distance from the clay in any angle)

  • Do all cables in the trench have the correct spacing according to the design?

  • Do all cables in the trench have the correct bend radius?

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.