Information
-
Audit Title
-
Document No.
-
Client / Site
-
Conducted on
-
Prepared by
-
Location
-
Personnel
PROJECT DETAILS
-
Project
-
Project Number
-
Supplier
-
Sub-Contractor
-
Supplier Contact
-
Description Of Inspection
-
Inspection Engineer (Inspected By)
- Biju Kurian Pottayil
- Simon Rigg
- Lloyd
- Danny D
- Collin
- Clay
- Barry Ebert
DETAILS OF INSPECTION
-
Materials/Equipments Inspected :
-
CV651-Base Frame - Drg C33029, C33027 Sheet 1 & Sheet 2, C33015
- Cut
- Fabrication Completed
- Internal Welding Completed & Inspected
- External Welding Completed
- Stress Relieved
- As Built Dimensions Checked
- Machining Completed and reports in MDR
- Released for Surface treatment
- Final Inspection & IRC Issued
-
CV651-Bracket APU Enclosure x 2 off - E34432
- Cut
- Fabrication Completed
- Internal Welding Completed & Inspected
- External Welding Completed
- Stress Relieved
- As Built Dimensions Checked
- Machining Completed and reports in MDR
- Released for Surface treatment
- Final Inspection & IRC Issued
-
CV651-Fasteners item 3,4,5 - As per Drg C33029
- Cut
- Fabrication Completed
- Internal Welding Completed & Inspected
- External Welding Completed
- Stress Relieved
- As Built Dimensions Checked
- Machining Completed and reports in MDR
- Released for Surface treatment
- Final Inspection & IRC Issued
-
CV511 - Base Frame - As Per Drg C33024 1,2 & 3
- Cut
- Fabrication Completed
- Internal Welding Completed & Inspected
- External Welding Completed
- Stress Relieved
- As Built Dimensions Checked
- Machining Completed and reports in MDR
- Released for Surface treatment
- Final Inspection & IRC Issued
-
CV521 - Base Frame - As Per Drg C33024 1,2 & 3
- Cut
- Fabrication Completed
- Internal Welding Completed & Inspected
- External Welding Completed
- Stress Relieved
- As Built Dimensions Checked
- Machining Completed and reports in MDR
- Released for Surface treatment
- Final Inspection & IRC Issued
-
CV514 - Base Frame - As Per Drg C33024 1,2 & 3
- Cut
- Fabrication Completed
- Internal Welding Completed & Inspected
- External Welding Completed
- Stress Relieved
- As Built Dimensions Checked
- Machining Completed and reports in MDR
- Released for Surface treatment
- Final Inspection & IRC Issued
-
CV524 - Base Frame - As Per Drg C33024 1,2 & 3
- Cut
- Fabrication Completed
- Internal Welding Completed & Inspected
- External Welding Completed
- Stress Relieved
- As Built Dimensions Checked
- Machining Completed and reports in MDR
- Released for Surface treatment
- Final Inspection & IRC Issued
-
CV853 - Base Frame - As Per Drg C33205 1,2 & 3
- Cut
- Fabrication Completed
- Internal Welding Completed & Inspected
- External Welding Completed
- Stress Relieved
- As Built Dimensions Checked
- Machining Completed and reports in MDR
- Released for Surface treatment
- Final Inspection & IRC Issued
-
CV853 - Bracket APU Enclosure x 2 off - As per Drg E34432
- Cut
- Fabrication Completed
- Internal Welding Completed & Inspected
- External Welding Completed
- Stress Relieved
- As Built Dimensions Checked
- Machining Completed and reports in MDR
- Released for Surface treatment
- Final Inspection & IRC Issued
-
CV854 - Base Frame - As per drg C33018 1,2 & 3
- Cut
- Fabrication Completed
- Internal Welding Completed & Inspected
- External Welding Completed
- Stress Relieved
- As Built Dimensions Checked
- Machining Completed and reports in MDR
- Released for Surface treatment
- Final Inspection & IRC Issued
-
CV854 - Bracket APU Enclosure x 2 off - As per Drg E34432 Rev 1
- Cut
- Fabrication Completed
- Internal Welding Completed & Inspected
- External Welding Completed
- Stress Relieved
- As Built Dimensions Checked
- Machining Completed and reports in MDR
- Released for Surface treatment
- Final Inspection & IRC Issued
-
CV854 - Plaque: Jack x 4 off - As per Drg E34190
- Cut
- Fabrication Completed
- Internal Welding Completed & Inspected
- External Welding Completed
- Stress Relieved
- As Built Dimensions Checked
- Machining Completed and reports in MDR
- Released for Surface treatment
- Final Inspection & IRC Issued
-
CV854 - Plaque: Bolt Torque - As per Drg E34191
- Cut
- Fabrication Completed
- Internal Welding Completed & Inspected
- External Welding Completed
- Stress Relieved
- As Built Dimensions Checked
- Machining Completed and reports in MDR
- Released for Surface treatment
- Final Inspection & IRC Issued
-
CV854 (Spare)- Base Frame - As per Drawing C33019 1 & 2
- Cut
- Fabrication Completed
- Internal Welding Completed & Inspected
- External Welding Completed
- Stress Relieved
- As Built Dimensions Checked
- Machining Completed and reports in MDR
- Released for Surface treatment
- Final Inspection & IRC Issued
-
CV854 (Spare)- Bracket APU Enclosure x 2 off- As per Drg E34432 Rev 1
- Cut
- Fabrication Completed
- Internal Welding Completed & Inspected
- External Welding Completed
- Stress Relieved
- As Built Dimensions Checked
- Machining Completed and reports in MDR
- Released for Surface treatment
- Final Inspection & IRC Issued
-
CV854 (Spare)- Plaque: Jack x 4 off- As per Drg E34190
- Cut
- Fabrication Completed
- Internal Welding Completed & Inspected
- External Welding Completed
- Stress Relieved
- As Built Dimensions Checked
- Machining Completed and reports in MDR
- Released for Surface treatment
- Final Inspection & IRC Issued
-
CV854 (Spare)- Plaque: Bolt Torque- As per Drg E34191
- Cut
- Fabrication Completed
- Internal Welding Completed & Inspected
- External Welding Completed
- Stress Relieved
- As Built Dimensions Checked
- Machining Completed and reports in MDR
- Released for Surface treatment
- Final Inspection & IRC Issued
-
CV852 - Base Frame - As per Drawing C33019 1 & 2
- Cut
- Fabrication Completed
- Internal Welding Completed & Inspected
- External Welding Completed
- Stress Relieved
- As Built Dimensions Checked
- Machining Completed and reports in MDR
- Released for Surface treatment
- Final Inspection & IRC Issued
-
CV852 - Bracket APU Enclosure x 2 off- As per Drg E34432 Rev 1
- Cut
- Fabrication Completed
- Internal Welding Completed & Inspected
- External Welding Completed
- Stress Relieved
- As Built Dimensions Checked
- Machining Completed and reports in MDR
- Released for Surface treatment
- Final Inspection & IRC Issued
-
CV852 - Plaque: Jack x 4 off- As per Drg E34190
- Cut
- Fabrication Completed
- Internal Welding Completed & Inspected
- External Welding Completed
- Stress Relieved
- As Built Dimensions Checked
- Machining Completed and reports in MDR
- Released for Surface treatment
- Final Inspection & IRC Issued
-
CV852 - Plaque: Bolt Torque- As per Drg E34191
- Cut
- Fabrication Completed
- Internal Welding Completed & Inspected
- External Welding Completed
- Stress Relieved
- As Built Dimensions Checked
- Machining Completed and reports in MDR
- Released for Surface treatment
- Final Inspection & IRC Issued
-
CV852 (Spare)- Base Frame - As per Drawing C33019 1 & 2
- Cut
- Fabrication Completed
- Internal Welding Completed & Inspected
- External Welding Completed
- Stress Relieved
- As Built Dimensions Checked
- Machining Completed and reports in MDR
- Released for Surface treatment
- Final Inspection & IRC Issued
-
CV852 (Spare)- Bracket APU Enclosure x 2 off- As per Drg E34432 Rev 1
- Cut
- Fabrication Completed
- Internal Welding Completed & Inspected
- External Welding Completed
- Stress Relieved
- As Built Dimensions Checked
- Machining Completed and reports in MDR
- Released for Surface treatment
- Final Inspection & IRC Issued
-
CV852 (Spare)- Plaque: Jack x 4 off- As per Drg E34190
- Cut
- Fabrication Completed
- Internal Welding Completed & Inspected
- External Welding Completed
- Stress Relieved
- As Built Dimensions Checked
- Machining Completed and reports in MDR
- Released for Surface treatment
- Final Inspection & IRC Issued
-
CV852 (Spare)- Plaque: Bolt Torque - As per Drg E34191
- Cut
- Fabrication Completed
- Internal Welding Completed & Inspected
- External Welding Completed
- Stress Relieved
- As Built Dimensions Checked
- Machining Completed and reports in MDR
- Released for Surface treatment
- Final Inspection & IRC Issued
-
Add media
-
Standards/Specifications Applicable
-
Drawing Numbers Applicable
INSPECTION/EXPEDITING DETAILS & COMMENTS
DOCUMENTATION STATUS
-
Contract Documents Available
-
ITP's Current Rev & Approval Status
-
Drawings Current & AFC
-
Manufacturing Schedules current Rev
-
Contractor's Procedure Available
RAW MATERIALS
-
All Materials Received
-
All Materials Stored correctly
-
All Material Certificates Received
INSPECTION & TEST STATUS
-
All Materials Conforming
-
NCR's Raised (NCR Numbers)
-
Non-Conforming item's disposition
-
Non-Conforming items identified & Segregated
IN-PROCESS INSPECTION & TEST STATUS
-
All materials inspected on receipt
-
ITP's progressively signed
-
ITP Hold & Witness Points attended
-
Inspection & Test Records verified
-
NDT by authorized personnel
-
Inspection, Measuring & Test Equipment calibrated
MANUFACTURING STATUS
-
All Work done safely
-
Resources available for completing job on time
-
SKM jobs prioritized to avoid any potential delays on contract
-
Appropriate number of personnel on job
-
Appropriate supervision on job
-
Progress in accordance with Schedule
-
Add media
-
Technical Queries recorded on Register
-
Technical Queries outstanding
-
ITP & MDR Status reflect current job status
HANDLING, STORAGE & PACKAGING
-
Materials and equipment are handled as per the contract requirement
-
Materials and equipment stored safely and in designated areas<br>
-
Packing and Protection in accordance with contract
TRANSPORT
-
Inspection Release Certificate completed and issued to Contractor and QA/QC Supt:
-
Consignment Note complete and accurate
-
IRC and Con Note affixed to goods/equipment
-
Goods/equipment marked in accordance with contract
-
Equipment loaded and secured on transport in accordance with contract
COMPONENTS/MATERIALS
-
Estimated overall Percent Complete
-
All Materials Ordered (No materials outstanding to be ordered)
-
All Materials Delivered to Contractors Facility
INSPECTION STAGE
-
Inspection Status
-
Inspection Engineer Signature
-
Signed On