Title Page
-
Job No.
-
Site Location
-
Client
-
Conducted on
-
Prepared by
-
Location
-
List Irwin M&E Personnel on Site
Coronavirus - Covid-19
-
IME operative is not displaying symptoms of Covid-19 (New continuous cough and/or a high temperature, shortness of breath or a change or loss in sense of smell or taste).
-
As per government guidance ensure the operative leaves site immediately, returns home and self-isolates as required.
-
The operative has been issued with Covid-19 Guidance and Procedures?
-
IME operative is cleaning down work areas/tools/equipment regularly and on completion of every shift
-
IME operative can carry out all tasks whilst adhering to social distancing?
-
Tasks where social distancing cannot be achieved are only permitted to be carried out where a specific risk assessment has been carried out and the task is essential.
Paper Work & Work Area
-
Has operative/s and/or personnel signed into site?
-
Does operative/s have site specific works order?
-
Has operative completed a POWRA prior to the works commencing?
-
Has the POWRA been created within the last 5 days?
-
Has all risks identified been controlled adequately?
-
Take a picture of POWRA
-
Have operatives been briefed on Emergency Procedures? (Including Evacuation Plan & Location of Muster Point)
-
Are COSHH Assessments available for ALL hazardous substances on site?
-
Are there Sub-Contractors on site?
-
Have all Sub-Contractors been approved by Irwin M&E?
-
Have they provided Risk Assessments/Method Statements for the works?
-
Does the sub contractor/s present have the relevant security clearances?
-
Does all employees on site carry CSR/CSCS cards and have relevant training?
-
Does this job operate a Permit to Work System?
-
Attach a photo of a recent Permit
-
Is there adequate access and egress throughout site?
-
Does Irwin M&E personnel display good housekeeping on site?
-
Has all Materials been stored appropriately on site?
Working at Height
-
Are Ladders/Steps being used on site?
-
Are they in good condition?
-
Are they being used appropriately?
-
Are Podium Steps being used on site?
-
Are they in good condition?
-
Are they being used appropriately?
-
Are Hop Up Steps being used on site?
-
Are they in good condition?
-
Are they being used appropriately?
-
Is Irwin M&E personnel using Mobile Tower Scaffolding on site?
-
Was the Mobile Tower Scaffold erected by a PASMA trained/competent person?
-
Has Mobile Tower Scaffold been erected correctly with Scaff Tags in place?
-
Attach a photo of Scaff Tags
-
Is Irwin M&E personnel using MEWPS (Scissor lift/Cherry picker/Boom lift) on site?
-
Is the operative IPAF trained to the correct level? (1B/3A/3B)
-
If hired - Is there a maintenance record within the MEWP?
-
Has a Working at Height Rescue Plan been completed prior to works commencing?
-
Attach a photo of Working at Height Rescue Plan
-
Are adequate safety precautions being taken? (E.g. Harness/Lanyard, Outriggers, Guard Rails)
Equipment, Tools & Company Vehicles
-
Are Operatives wearing the required PPE?
-
Are Power Tools in good condition?
-
Has Portable Appliance Testing (PAT) been carried out in the last 6 months?
-
Attach photo of PAT sticker
-
Do engineers require a Lock Out Tag Out (LOTO) Kit?
-
Is LOTO Kit present on site?
-
Do engineers require Mechanical/Electrical Test Equipment on site?
-
List associated equipment
-
Has the equipment been tested In-house within this last 6 months? Or calibrated within this past year?
-
Attach a photo of most recent In-house test/Calibration sticker
-
Is there a company vehicle on site?
-
Take a picture of the registration
-
Is there any visual damage around the vehicle ? (Check all panels, sides and take pictures)
-
Are tyres in good condition (please use tyre thread checker, tyres should be (2mm and above any less than 2mm should be replaced)
-
Is the internal contents of the vehicle in a reasonable condition?
-
Is there an in-date/stocked First Aid Kit on site?
-
Is there a Fire Extinguisher on site? (All Irwin M&E vans should have 2kg Powder Extinguisher)
-
Has the Fire Extinguisher been serviced within the last year?
-
Is there any issues needing/have been discussed with Main Contractor/Client?
-
Are there any other issues/queries/requests presented by the operative?
Closing Out
-
Has findings of the audit been discussed with manager/site supervisor/operative?
-
Signature of person conducting audit.