  • Job Number:

  • Site Location

  • Client Name

  • Conducted on

  • Inspected by

  • Site Supervisor

  • List Irwin M&E personnel and subcontractors on site:

Coronavirus - Covid-19

  • No IME operative is displaying symptoms of Covid-19 (New continuous cough and/or a high temperature or shortness of breath).

  • As per government guidance ensure the operative leaves site immediately, returns home and self-isolates as required.

  • Have IME Site RAMS been updated to include site specific procedures?

  • Have all IME operatives been re-inducted to site and had updated RAMS communicated to them?

  • Have Sub-Contractors RAMS been updated to include site specific procedures?

  • Are site procedures i.e. social distancing measures/enhanced cleaning regimes being enforced on site?

  • This must be reported to IME H&S Dept immediately and site assessed to determine whether works can continue.

  • Are IME operatives cleaning down work areas/tool/equipment regularly and on completion of every shift?

  • IME operatives are not completing tasks where social distancing cannot be achieved?

  • Tasks where social distancing cannot be achieved are only permitted to be carried out where a specific risk assessment has been carried out and the task is essential.

Site Folder and Paperwork

  • Have corrective actions from previous audit been completed?

  • Is there a Site File on site?

  • Have all engineers and personnel signed into site?

  • Have all engineers been Inducted to site?

  • Are Induction forms completed fully (with all areas completed)?

  • Add a photo of completed Induction forms

  • Is there a Safe system of work and Risk Assessments available on site corresponding to the works?

  • Is the Safe System of Work in date?

  • Has the Safe system of work been read/understood & signed by all engineers?

  • Take a photo of signed Safe system of work.

  • Are there Sub-Contractors on site?

  • Have they been approved by Irwin M&E?

  • Have they provided adequate Risk Assessments/Method Statements/clearance for the works?

  • Does all employees on site carry CSR/CSCS cards and relevant training?

  • Are COSHH assessments available for ALL hazardous substances on site?

  • Does this job operate a Permit to Work system?

  • Take photo of permit to work

  • Have weekly Working at Height (Ladder/Steps/Scaffold) checks been completed?

  • Are weekly Toolbox Talks being carried out ?

Working Area

  • Is there adequate access and egress throughout site?

  • Does Irwin M&E personnel display good housekeeping on site?

  • Have all materials been stored appropriately on site?

  • Is adequate Safety Signage displayed on place?

  • Are Emergency Procedures in place?

  • Are Irwin M&E producing waste on site?

  • How is waste being disposed of? (Make Note)

Working at Height

  • Are Ladders/Steps steps being used on site?

  • Are they in good condition?

  • Are they being used appropriately?

  • Are Podium Steps being used on site?

  • Are they in good condition?

  • Are they being used appropriately?

  • Are Hop Up Steps being used?

  • Are they in good condition?

  • Are they being used appropriately?

  • Are Irwin M&E personnel using Mobile Tower Scaffolding on site?

  • Was the Mobile Tower Scaffold erected by a PASMA trained/competent person?

  • Has the Mobile Tower Scaffold been erected correctly with Scaff Tags in place?

  • Take a photo of Scaff tag

  • Are Irwin M&E using MEWPs (Scissor lift/Cherry picker/Boom lift) on site?

  • Is the operative IPAF trained to the correct level? (1B/3B/3B)

  • If hired - Is there a maintenance record within the MEWP?

  • Has a Working at Height Rescue Plan been completed prior to works commencing?

  • Take a photo of Working at Height Rescue Plan

  • Are weekly MEWPS inspections been carried out?

Equipment/Tools

  • Are Operatives wearing the required PPE?

  • Are Power Tools in good general condition?

  • Are weekly HAV checks being completed if applicable?

  • Has a Portable Appliance Test (PAT) been carried out in the last 3 months?

  • Attach photo of PAT sticker

  • Is a Lock Out Tag Out (LOTO) kit required on site?

  • Is there a LOTO Kit on site?

  • Do engineers require Mechanical/Electrical test equipment on site?

  • List associated equipment

  • Has the equipment been tested in-house within the last 6 months or calibrated within the past year?

  • Attach a photo of most recent in-house test/calibration sticker

  • Is there an in-date/stocked First Aid kit on site?

  • Are there adequate Fire Extinguishers on site?

  • Have they been serviced within the last year?

  • Are there any other Contractor Issues on site directly affecting Irwin M&E?

  • Are there any other issues/queries/requests presented on-site?

Closing Out

  • Has findings of the audit been discussed with manager/site supervisor/operative?

  • Signature of person conducting audit

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.