  • Project:

  • Site Address
  • Contractors Build Complete Date

  • Absolute Completion Date

  • Branch Go Live Date

  • Prepared by

  • Site Manager

  • Audit Conducted on

  • Project Manger Signature

Attendees

  • Please select attendees of security sign off meeting

  • Please add any additional attendees not listed above

  • Please add attendees of MEP & Fit Out Sign off Meeting

  • Please add any additional attendees not listed above

Security

Security

  • Are all CCTV works complete & fully operational?

  • Please add photos of CCTV cabinet & all monitor images

  • Details of what works are outstanding & why

  • Please add photos of incomplete works

  • Add projected completion date

  • Will incomplete works effect commissioning activities?

  • Details of Impact

  • Will incomplete works impact AC / Branch Go Live

  • Details of impact

  • Are all physical security works complete? e.g.. Perimeter alarms, detectors & security bars

  • Please add photos of completed install

  • Details of what works are outstanding & why

  • Please add photos of incomplete works

  • Add projected completion date

  • Will incomplete works effect commissioning activities?

  • Details of Impact

  • Will incomplete works impact AC / Branch Go Live

  • Details of impact

  • Are all self service machines & safes alarmed with HUA ready to be deployed?

  • Please add photos of completed install

  • Details of what works are outstanding & why

  • Please add photos of incomplete works

  • Add projected completion date

  • Will incomplete works effect commissioning activities?

  • Details of Impact

  • Will incomplete works impact AC / Branch Go Live

  • Details of impact

  • Has RSM completed his / her security inspection to allow bullion run

  • Please add photo of RSM Sign off

  • Details of what works are outstanding & why

  • Please add photos of incomplete works

  • Add projected completion date

  • Will incomplete works effect bullion run?

  • Details of Impact

  • Where any additional works requested by RSM?

Technology Commissioning Readiness

Technology Commissioning Readiness

  • Is Comms cabinet live?

  • Please add photos of live comms

  • Details of what works are outstanding & why

  • Please add photos of incomplete works

  • Add projected completion date

  • Will incomplete works effect commissioning activities?

  • Details of Impact

  • Will incomplete works impact AC / Branch Go Live

  • Details of impact

  • Is there any missing furniture that will effect IT install & commissioning?

  • Please add details of issue

  • Add projected completion date

  • Please add details of temporary plan if required

  • Have all Patching details been provided to Tech Team?

  • Details of why these have not been issued

  • Add date these will be issued

  • Will incomplete works effect commissioning activities?

  • Details of Impact

  • Will incomplete works impact AC / Branch Go Live

  • Details of impact

  • Do all self service machines have live power & data supplies

  • Please add photos of live kit

  • Details of what works are outstanding & why

  • Please add photos of incomplete works

  • Add projected completion date

  • Will incomplete works effect commissioning activities?

  • Details of Impact

  • Will incomplete works impact AC / Branch Go Live

  • Details of impact

Mechanical & Electrical Readiness

Mechanical & Electrical Readiness

  • Are all air conditioning works complete & fully operational?

  • Please add photos of all control panels, internal & external units

  • Details of what works are outstanding & why

  • Please add photos of incomplete works

  • Add projected completion date

  • Will incomplete works effect commissioning activities?

  • Details of Impact

  • Will incomplete works impact AC / Branch Go Live

  • Details of impact

  • Are all electrical works complete. Inc. lighting etc.

  • Please add photos of completed install

  • Details of what works are outstanding & why

  • Please add photos of incomplete works

  • Add projected completion date

  • Will incomplete works effect commissioning activities?

  • Details of Impact

  • Will incomplete works impact AC / Branch Go Live

  • Details of impact

  • Is RMBS / SMART Install complete?

  • Please add photos of completed install

  • Details of what works are outstanding & why

  • Please add photos of incomplete works

  • Add projected completion date

  • Will incomplete works effect commissioning activities?

  • Details of Impact

  • Will incomplete works impact AC / Branch Go Live

  • Details of impact

  • Where any additional works requested by Realy's TSM at CBC

  • Has Realys TSM Snagging list been issued?

  • Please list quantity of snags raised

  • Provide Details of why this has not been issued

Fire Alarm Readiness

Fire Alarm Readiness

  • Is fire alarm system installed & operational ahead of commissioning?

  • Please add photos of completed work & live fire panel

  • Details of what works are outstanding & why

  • Please add photos of incomplete works

  • Add projected completion date

  • Will incomplete works effect commissioning activities?

  • Details of Impact

  • Will incomplete works impact AC / Branch Go Live

  • Details of impact

Fit Out, Furniture & Branding

Fit Out, Furniture & Branding

  • Are all fit out works complete

  • Please add photos key areas complete

  • Details of what works are outstanding & why

  • Please add photos of incomplete works

  • Add projected completion date

  • Will incomplete works effect commissioning activities?

  • Details of Impact

  • Will incomplete works impact AC / Branch Go Live

  • Details of impact

  • Is all furniture installed?

  • Please add photos of completed install

  • Details of what works are outstanding & why

  • Please add photos of incomplete works

  • Add projected completion date

  • Will incomplete works effect commissioning activities?

  • Details of Impact

  • Will incomplete works impact AC / Branch Go Live

  • Details of impact

  • Are all internal & external branding works complete?

  • Please add photos of completed install

  • Details of what works are outstanding & why

  • Please add photos of incomplete works

  • Add projected completion date

  • Will incomplete works impact AC / Branch Go Live

  • Where any additional works requested by Realy's / Barclays

Building Control sign Off & FRA Arrangements

Building Control sign Off & FRA Arrangements

  • Has Building Control final sign off visit been arrange pre AC

  • Please Confirm Date - Must be before AC

  • Please confirm reasons why visit cannot be carried out pre AC

  • Has BV FRA visit been arranged pre AC

  • Please Confirm Date - Must be before AC

  • Please confirm reasons why visit cannot be carried out pre AC

Staff Health & Welfare

Staff Health & Welfare Readiness

  • Is all fire signage in place?

  • Please add photos of completed works

  • Details of what works are outstanding & why

  • Please add photos of incomplete works

  • Add projected completion date

  • Will incomplete works impact AC / Branch Go Live

  • Details of impact

  • Have ISS delivered all relevant supplies? e.g. toilet roll, paper towels, sanitary bins, soap, bin bags

  • Please add photos of completed install

  • Details of what works are outstanding & why

  • Please add photos of incomplete works

  • Add projected completion date

Summary of Snagging & Outstanding Works at CBC

Snagging & Outstanding Works at CBC

  • Contractors MEP Snagging list must be produced & issued at Directors Handover

  • Add details of number of snags & close out plan

  • Have all Contractor snags been closed out by CBC

  • Please list outstanding snags

  • Fit Out Snagging list must be produced & issued at Directors Handover

  • Add details of number of snags & close out plan

  • Have all Contractor snags been closed out by CBC?

  • Please list outstanding snags

  • Realy's TSM Snagging list must be issued at CBC meeting

  • Add details of number of snags & close out plan

  • ISG PM must produce a draft Close out tracker to be issued at CBC meeting

  • Add details of number of snags & close out plan

  • Has close out tracker been issued to relevant contractors?

  • Have close out dates for all items been confirmed by contractors

  • List details of why dates cannot be confirmed.

  • Are there any items that may be outstanding at AC?

  • Add details of what may be outstanding

CBC Document Issue Checklist - All to be issued the day after CBC

  • ISG Contractors Build Complete Audit.

  • MEP Updated Snagging Audit

  • Fit Out Updated Snagging Audit

  • Draft Close Out Tracker

  • Realys TSM Snag List

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.