Information
-
Document No.
-
Audit Title
-
Client / Site
-
Conducted on
-
Prepared by
-
Location
-
Personnel
Mechanical Checklist
Mounting Frame and Fixing of Modules
-
Is single fix inserted as per drawing, flat and on opposite crowns?
-
Add media
-
Has EPDM Pads being inserted, if required underneath rail?
-
Add media
-
Is rail firmly inserted onto rail and end caps installed on each row?
-
Add media
-
Is there a minimum of 50mm overhang on rail from end of each module?
-
Add media
-
Is all mid clamps and end clamps in place on each module and firmly fixed into position?
-
Add media
-
Is there any defects picked on system that should be made known to contractor?
-
Add media
Electrical Checklist
Containment
-
Is exterior cable containment hot dip galvanised, all cuts sprayed and free from sharp edges?
-
Add media
-
Is cables fixed onto tray, and cable tied at distance fo no more than 1.5m apart?
-
Add media
-
Is containment bonded, if required to the local earthing system?
-
Add media
AC/DC Installation
-
Is inverters securely fixed to wall, with manufacturer spacing between each inverter?
-
Add media
-
Has appropriate rated AC isolator switch being installed beside inverter?
-
Add media
-
Is labelling being installed to identify strings as per the design drawing?
-
Add media
-
Has labelling being installed on cables/containment?
-
Add media
-
Has AC Cabling being run in a neat manner to breaker on distribution board
-
Add media