Operator Name
-
Evaluator Name
-
Evaluation Date
-
Crane make/model used during evaluation
-
Task performed during evaluation
Evaluation Checklist
-
Assembly / Disassembly Operations
-
Crane setup for operations
-
Cribbing / matting setup
-
Crane leveling (daily verification)
-
Adequately identified and avoided existing underground utilities
-
Crane setup / positioned to reduce boom radius requirements
-
Tail swing clearance verified
-
Swing radius protection in place
-
Fueling operations
-
Pre-use inspection
-
Performed pre-lift testing and requirements for personnel basket use
-
Demonstrated knowledge is weather affects of crane operation
-
Safely mounted and dismounted crane
-
Able to determine load weight
-
Properly evaluated and utilized load chart / line capacity
-
Demonstrate knowledge in rigging requirements
-
Utilized a tag line on all lifts except where it presented additional hazards
-
Positioned boom to the center of gravity of load
-
Adjusted boom for deflection prior to lift
-
Demonstrated knowledge in standard signals
-
Ensure safe swing path is maintained during lift (obstructions/personnel)
-
Operated the crane within its operational limitations / maintained operational control
-
Maintained safe operations regarding two-blocking the crane
-
Minimized dynamic loading during crane operations
-
Safely traveled crane with / without load
-
Kept personnel from hazardous areas during operation
-
Maintained adequate distance from electrical lines or had other required controls in place
-
Loaded/Unloaded trucks using safe work practices
-
Did not leave crane unattended while loaded
-
Performed dry run for critical lifts
-
Performed PM / Grease maintenance as required
-
Based on my evaluation the operator:
-