Information
-
Audit Title
-
Site
-
Location
-
Contractor/s
-
Conducted on
-
Audit conducted by
-
Other Personnel Present
General
-
Has the contract been signed and submitted?
-
Has the Contractor provided the Bank Guarantees?
-
Have you erected "Notice of Roadworks" signage?
-
Have you completed a letter drop to relevant stakeholders prior to Works commencing?
-
Have works been advertised in weekly Council Noticeboard in Latrobe Express?
-
Have you notified the Coordinator of Civil Works that Works will be commencing?
-
Have you arranged a Pre-Start meeting with the Contractor?
-
Have you received and approved all relevant documentation from the Contractor? (OH&S Docs, SWMS, ITP's, EMP, PMP, etc)
-
If an EMP is required, has it been approved?
Traffic Management
-
Have you had the Traffic Management Plan and the MoA reviewed by the Traffic Engineer?
-
Is VicRoads approval Required?
-
Is a VicRoads Working Within Road Reserves Form required?
-
Have you had the MoA approved by the General Manager?
Emergency Services, Garbage Trucks and Bus Routes
-
Have you notified the Emergency Services (Ambulance, Police, Fire and SES) about the Works and supplied them with a copy of the Traffic Management Plan?
-
Have you notified Cleanaway of the up coming Works (look up bin days and routes on Council page)?
-
Is there a bus route through the work site? If so, notify LV bus lines.
-
Is there a bus stop on the construciton site? If so contact PTV and LV Bus Lines regarding closure or relocation of bus stop.
Pre-Works Site Inspection
-
Have you inspected the existing infrastructure? Take photos of footpaths, nature strips, fences, etc.
Audit Program
-
Have you set reminders in your calendar as per your audit program?