Information
-
HSG-RAS-008-Rev. 0/iA
-
Description
-
Client / Site
-
Conducted on
-
Prepared by
-
Location
-
Personnel
Customer liaison
-
Will the customer allow the electrical supply to be isolated for the during of the work to be carried out? (therefore no live working required)
-
If 'Yes' agree approximate start time & duration of task
-
If 'No' and live working is necessary for the duration of the task, how long will the task take?
-
Where the risk assessment deems that live working is not appropriate and agreement cannot be reach over a suitable time to allow the machine to be worked on isolated, the problem should be escalated.
-
Acceptance from the customer that the machine is unavailable and the electrical supply cannot be isolated, therefore work must be carried out whilst the system is still live.
-
Customer signature
-
Position
Risk assessment
-
A risk assessment must be completed for live electrical work. For any hazards which are not adequately controlled, isolation must take place.
-
Hazards, Panel condition, consider;
-
Exposed conductors?
-
Detail additional control measures required
-
Damaged wires / panel?
-
Detail additional control measures required
-
Water ingress?
-
Detail additional control measures required
-
Sharp objects?
-
Detail additional control measures required
-
Lint / dust?
-
Detail additional control measures required
-
Check surrounding area, consider;
-
Water
-
Detail additional control measures required
-
Slips / trip / falls (house keeping)
-
Detail additional control measures required
-
Lighting
-
Detail additional control measures required
-
Pedestrian access & walkways
-
Detail additional control measures required
-
Cages
-
Detail additional control measures required
-
Traffic movement
-
Detail additional control measures required
-
Overhead hazards / falling objects
-
Detail additional control measures required
-
Chemicals / oils / dirt
-
Detail additional control measures required
-
Moving / rotating parts
-
Detail additional control measures required
-
Working at height
-
Detail additional control measures required
-
Fire / explosive atmosphere
-
Detail additional control measures required
-
Additional hazard, give details
-
Detail additional control measures required
-
Additional hazard, give details
-
Detail additional control measures required
-
Additional hazard, give details
-
Detail additional control measures required
Completion of risk assessment
-
Is the risk acceptable to carry out work in live working?
-
Is accompaniment required?
-
Is escalation required?
-
Christeyns employee signature
-
Position