Lock up Check List
-
Job Number
-
Lot Address
-
Conducted on
-
Site Manager / Carpenter
-
Inspector
-
Location
FIRST INSPECTION
-
Did the job pass
REINSPECTION
-
Are all items complete
-
REINSPECTION CARRIED OUT BY
-
Select date
LANDSCAPE VIEW
-
Landscape view of all sides.
Site Safety
-
Site safety correct?
-
Site safety signs displayed & filled out correctly. Writing is clear?
-
ESP is displayed in meter box?
OVERALL GENERAL COMMENTS
Lock up Items
-
Check all reveals plumb straight and square
-
Check all bulkheads straight and square
-
Check bath and spa hobs for level and 510mm high
-
Spa 1700mm X 1000mm. Bath 1600mm X 700mm
-
Bath and spa cut out sized correct
-
Bath and spa flashing installed under villa board
-
Villa board nailed down with flat head nails and overhang 6mm on edge
-
Check walls and external corners for straightness
-
Packers to be feathered each end and nailed 150mm apart
-
Check for manhole and trim out if required
-
Meter box cleat and remove bracket if required
-
Install range hood noggins 1550mm - 2150mm between 3 studs
-
Install packer to entry short wall at bottom plate
-
Sweep out house remove shavings from plates
-
Install packer to entry short wall at bottom plate
-
Kitchen bulkhead back cleat
-
Pack rear of bulkheads 3mm lower than front edge
-
Install noggin for vanities if required at 800mm in powder room
-
Check obtuse corners for plumb
-
Door margins to be equal top, bottom and sides
-
Install all locks 1020mm and 1120mm from bottom of doors
-
Flush bolts fitted to entry doors
-
Temp doors hang and fit locks
-
All studs to be marked on floor
-
All rubbish to be placed in bin
-
Kitchen bulkhead back cleat
-
Any comments not covered by above categories