PROCESS
-
The Lock Out - Tag Out process is systematically applied when working on energized equipment
-
There is evidence / examples of recent LOTO
-
LOTO Procedure is well understood by Managers and Supervisors
-
LOTO Procedure is well understood by the Site Team
-
A list of activities subjected to LOTO is visibly posted, the personnel are aware and understand the list
-
All LOTO certificates are formally authorized by the Person In Charge
-
Contractors follow the LOTO procedure for services rendered on site.
-
LOTO is always completed before and referenced when Work is performed.
LOTO DEVICES
-
LOTO equipment (board) is readily available at all times?
-
Tags are waterproof to prevent tag from deteriorating or becoming illegible due to wet conditions and weather
-
Tags include legend such as Do Not Start, Do Not Open, Do Not Close, Do Not Energize, Do Not Operate
-
All isolation points are able to be isolated by positive means of locking
TRAINING
-
Personnel know the purpose and the use of the LOTO procedure
-
Energy isolation incidents / lessons learned are reviewed
-
All personnel are familiar with the LOTO supplemental checklists
-
Personnel recognize all type of energy sources requiring isolation through LOTO