Information
-
Job ID
-
Audit date
-
Auditor name
-
Auditee name
Desktop checks
2.000 Handover & collateral delivered to Chorus
-
2.022 Cable Plant Alteration (CPA) forms completed and correct
-
2.025 As Builts accurately reflect what was built
55.000 Network Records
-
55.026 Correct sized cable has been drawn and labelled as per As Built and matches NetMAP
-
55.102 Pole to Boundary form aligns to Lay plan
-
55.103 Records match what was built/completed in the field
Field checks
13.000 Cable haul
-
13.001 Correct cable installed as per project pack
15.000 cable and duct lay
-
15.002 Ducts laid or directional drilled between 450mm and 1000mm in footway
-
15.003 Ducts laid or directional drilled between 600mm and 1000mm in roadway
-
15.004 Duct alignment and configuration correct
-
15.005 Route position correct according to plan
-
15.007 Cable ends sealed with heat shrink
-
15.026 Duct at customer's boundary for direct install fibre sealed and buried or housed in appropriate enclosure
16.000 Micro duct directional drill and lay
-
16.002 Micro ducts laid or directional drilled between 450mm and 1000mm in footway
-
16.003 Micro duct laid or directional drilled between 600mm and 1000mm in roadway
-
16.005 Duct alignment and configuration correct
-
16.006 Route position correct according to plan
-
16.007 All micro duct ends of runs are sealed with end caps, then a closure fitted
-
16.008 Micro duct end on customer boundary (including ROW) capped, wrapped in heatshrink and labelled, then either buried or housed in appropriate enclosure
-
16.010 Micro duct joints to standard - approved enclosure, correct connectors, earth continuity maintained, water tight etc
-
16.026 1-way micro duct labelled correctly
-
16.027 Locate peg installed at buried lateral location or soft surface
17.000 Manhole, joint chamber and ducts (new and existing)
-
17.002 Manhole sited correctly, to plan and parallel to boundary line
-
17.003 Manhole correctly sized, as per design job spec
-
17.004 Manholes frames flush to ground, no trip hazard
-
17.010 All micro duct entry grouted, duct reamed, sits flush to wall
-
17.011 Non-concrete joint chamber duct entry protrudes 50mm into chamber, reamed and sealed to wall
-
17.012 Manhole cable management brackets installed to accept arms
-
17.013 Manhole cable management arms installed as required. Cable management correct
-
17.014 Manhole/joint chamber lids locked, in working order and rubber bung fitted
-
17.015 Ducts entry positioned close to adjacent wall for easy cable management
-
17.016 Ducts sealed where necessary to prevent ingress of water, moisture, gas, or pests into buildings and cabinets
-
17.021 New ducts into existing manholes - correct hole size and location cut in manhole wall for new duct entry
-
17.022 Direct fibre feed hauling tape installed
-
17.023 Direct fibre feed hauling tape secured at each end
-
17.027 Pit correctly bedded - metal surrounding sides of pit compacted
18.000 Manhole cable management
-
18.001 All cables managed tidily on brackets and arms
-
18.003 Fibre cable protection when required, tread plate, split sub-duct, bandit tape
39.000 Aerial terminal/OFDC
-
39.001 Correct terminal used
-
39.002 Terminal mounted and secured correctly
-
39.004 Terminal lid secure
-
39.013 Network labelling in place to suit requirements
-
39.014 Terminal on correct pole face
-
39.015 Flexi pipe secured directly below terminal (galv saddle on wooden pole)
-
39.016 Flexi pipe secured directly below terminal (bandit tape on concrete pole)
-
39.017 20mm or 32mm conduit secured to pole (wooden - galv saddles for White PVC pipe, plastic saddles for grey/beige 32mm HDPE pipe, secured with clouts or bandit straps. 600mm spacing)
-
39.018 20mm or 32mm conduit secured to pole, spacing < 1.5m (concrete bandit tapes)
-
39.019 Protective cable casing installed (as required - concrete or wood)
41.000 BDD terminal
-
41.001 Pit lids secure/locked, with bung fitted where appropriate
-
41.002 Pit installed correctly
42.000 Pedestal
-
42.001 Pedestal vertical, firm and at correct depth
-
42.003 Lid secure
-
42.008 Foam bung fitted/in correct position
-
42.019 Plastic bags secured, separate bags for loop/cable end and underground leads
-
42.025 Starter pipe(s) installed to facilitate provisioning of NGA Services
74.000 Hand holes
-
74.002 Hand hole locked, with lock facing the customer boundary and openable
-
74.003 Starter pipe(s) installed to facilitate provisioning of NGA services
-
74.004 Flush with ground
-
74.006 Lateral labelled and sealed. End cap and heat shrink applied
-
74.008 Lid free from concrete/ seal
-
74.009 Sited correctly (close to customer boundary, hard surface, foot traffic only)
-
74.010 Single way Ribbonet, 1 turn only, end sealed wit heat shrink
-
74.011 Maximum of 4 single way Ribbonets installed
-
74.014 30mm bend radius unconditionally observed at all locations
77.000 UFB Channell Flash 9 installation
-
77.001 50mm of inner black sheath past outer green sheath
-
77.003 Earth wire managed and secured to pit wall
-
77.006 Micro duct tubes routed correctly in pit - minimum bend radius not exceeded
-
77.008 Velcro ties secured to the pit wall
-
77.009 Locking collar on closure is secured with locking bolt. ID label facing upwards
-
77.011 Correct micro duct connectors used to join and seal micro duct (5mm and 12mm)
-
77.012 Correct size gas blocks installed on 12mm micro ducts outside of closure containing optic fibre cable
-
77.013 All spare or unallocated 5mm and 12mm micro ducts capped with duct end caps within closure and pit
-
77.017 Closure base 'O' ring clean, dry, undamaged and correctly sealed. Spare O ring in closure
-
77.019 Pit lid free of reinstatement materials(T/seal cone)
-
77.020 All 5mm micro ducts trimmed to 80mm in height from base
-
77.021 All 12mm micro ducts trimmed to 40mm in height from base
-
77.022 Lid closure labelled correctly with NetMap ID and facing upwards
-
77.023 12mm micro duct carrying cable is correctly labelled with NetMap elements
-
77.027 All microducts are labelled
-
77.029 Joint bundle wrapped in Eziwrap or A3 - 250 micron clear plastic and secured
-
77.042 Micro ducts 1 - 26 enter through 3 RH ports (viewed from swing arm)
-
77.044 100mm duct capped at pole
-
77.046 Minimum bend radius achieved inside pit (149mm for 116f, 110mm for 48f)
-
77.051 Enclosure support bracket in place
-
77.052 Tray retention strap in place
-
77.061 Chamber lid secured
-
ABFFP photos
-
77.064 Water ingress - no water access to closure
-
77.065 End stops on all 5mm and 12mm tubes
-
End Cap Photos
-
77.066 5mm divisible seals on all working trays
-
77.067 Pressure testing completed
General Workmanship checks
6.000 Work Areas & Safety
-
6.009 Joint chamber/manhole lid closed and secure
-
6.014 Any defects to existing network outside of scope of project referred to be rectified in the future
-
6.015 All power clearances maintained (underground and overground)
72.000 Reinstatement
-
72.001 Properly damage made good
-
72.014 Any road markings damaged by works are restored
-
72.018 Ground reinstatement completed
-
72.020 Surplus soil removed
-
72.021 Reseal completed - footway / vehicle resurfaced
-
72.028 Reinstatement completed to standard
73.000 Site tidy
-
73.001 Site tidy, no task waste - poles
-
73.024 Site tidy, no task waste - general