Information

  • Job ID

  • Audit date

  • Auditor name

  • Auditee name

Desktop checks

2.000 Handover & collateral delivered to Chorus

  • 2.022 Cable Plant Alteration (CPA) forms completed and correct

  • 2.025 As Builts accurately reflect what was built

55.000 Network Records

  • 55.026 Correct sized cable has been drawn and labelled as per As Built and matches NetMAP

  • 55.102 Pole to Boundary form aligns to Lay plan

  • 55.103 Records match what was built/completed in the field

Field checks

13.000 Cable haul

  • 13.001 Correct cable installed as per project pack

15.000 cable and duct lay

  • 15.002 Ducts laid or directional drilled between 450mm and 1000mm in footway

  • 15.003 Ducts laid or directional drilled between 600mm and 1000mm in roadway

  • 15.004 Duct alignment and configuration correct

  • 15.005 Route position correct according to plan

  • 15.007 Cable ends sealed with heat shrink

  • 15.026 Duct at customer's boundary for direct install fibre sealed and buried or housed in appropriate enclosure

16.000 Micro duct directional drill and lay

  • 16.002 Micro ducts laid or directional drilled between 450mm and 1000mm in footway

  • 16.003 Micro duct laid or directional drilled between 600mm and 1000mm in roadway

  • 16.005 Duct alignment and configuration correct

  • 16.006 Route position correct according to plan

  • 16.007 All micro duct ends of runs are sealed with end caps, then a closure fitted

  • 16.008 Micro duct end on customer boundary (including ROW) capped, wrapped in heatshrink and labelled, then either buried or housed in appropriate enclosure

  • 16.010 Micro duct joints to standard - approved enclosure, correct connectors, earth continuity maintained, water tight etc

  • 16.026 1-way micro duct labelled correctly

  • 16.027 Locate peg installed at buried lateral location or soft surface

17.000 Manhole, joint chamber and ducts (new and existing)

  • 17.002 Manhole sited correctly, to plan and parallel to boundary line

  • 17.003 Manhole correctly sized, as per design job spec

  • 17.004 Manholes frames flush to ground, no trip hazard

  • 17.010 All micro duct entry grouted, duct reamed, sits flush to wall

  • 17.011 Non-concrete joint chamber duct entry protrudes 50mm into chamber, reamed and sealed to wall

  • 17.012 Manhole cable management brackets installed to accept arms

  • 17.013 Manhole cable management arms installed as required. Cable management correct

  • 17.014 Manhole/joint chamber lids locked, in working order and rubber bung fitted

  • 17.015 Ducts entry positioned close to adjacent wall for easy cable management

  • 17.016 Ducts sealed where necessary to prevent ingress of water, moisture, gas, or pests into buildings and cabinets

  • 17.021 New ducts into existing manholes - correct hole size and location cut in manhole wall for new duct entry

  • 17.022 Direct fibre feed hauling tape installed

  • 17.023 Direct fibre feed hauling tape secured at each end

  • 17.027 Pit correctly bedded - metal surrounding sides of pit compacted

18.000 Manhole cable management

  • 18.001 All cables managed tidily on brackets and arms

  • 18.003 Fibre cable protection when required, tread plate, split sub-duct, bandit tape

39.000 Aerial terminal/OFDC

  • 39.001 Correct terminal used

  • 39.002 Terminal mounted and secured correctly

  • 39.004 Terminal lid secure

  • 39.013 Network labelling in place to suit requirements

  • 39.014 Terminal on correct pole face

  • 39.015 Flexi pipe secured directly below terminal (galv saddle on wooden pole)

  • 39.016 Flexi pipe secured directly below terminal (bandit tape on concrete pole)

  • 39.017 20mm or 32mm conduit secured to pole (wooden - galv saddles for White PVC pipe, plastic saddles for grey/beige 32mm HDPE pipe, secured with clouts or bandit straps. 600mm spacing)

  • 39.018 20mm or 32mm conduit secured to pole, spacing < 1.5m (concrete bandit tapes)

  • 39.019 Protective cable casing installed (as required - concrete or wood)

41.000 BDD terminal

  • 41.001 Pit lids secure/locked, with bung fitted where appropriate

  • 41.002 Pit installed correctly

42.000 Pedestal

  • 42.001 Pedestal vertical, firm and at correct depth

  • 42.003 Lid secure

  • 42.008 Foam bung fitted/in correct position

  • 42.019 Plastic bags secured, separate bags for loop/cable end and underground leads

  • 42.025 Starter pipe(s) installed to facilitate provisioning of NGA Services

74.000 Hand holes

  • 74.002 Hand hole locked, with lock facing the customer boundary and openable

  • 74.003 Starter pipe(s) installed to facilitate provisioning of NGA services

  • 74.004 Flush with ground

  • 74.006 Lateral labelled and sealed. End cap and heat shrink applied

  • 74.008 Lid free from concrete/ seal

  • 74.009 Sited correctly (close to customer boundary, hard surface, foot traffic only)

  • 74.010 Single way Ribbonet, 1 turn only, end sealed wit heat shrink

  • 74.011 Maximum of 4 single way Ribbonets installed

  • 74.014 30mm bend radius unconditionally observed at all locations

77.000 UFB Channell Flash 9 installation

  • 77.001 50mm of inner black sheath past outer green sheath

  • 77.003 Earth wire managed and secured to pit wall

  • 77.006 Micro duct tubes routed correctly in pit - minimum bend radius not exceeded

  • 77.008 Velcro ties secured to the pit wall

  • 77.009 Locking collar on closure is secured with locking bolt. ID label facing upwards

  • 77.011 Correct micro duct connectors used to join and seal micro duct (5mm and 12mm)

  • 77.012 Correct size gas blocks installed on 12mm micro ducts outside of closure containing optic fibre cable

  • 77.013 All spare or unallocated 5mm and 12mm micro ducts capped with duct end caps within closure and pit

  • 77.017 Closure base 'O' ring clean, dry, undamaged and correctly sealed. Spare O ring in closure

  • 77.019 Pit lid free of reinstatement materials(T/seal cone)

  • 77.020 All 5mm micro ducts trimmed to 80mm in height from base

  • 77.021 All 12mm micro ducts trimmed to 40mm in height from base

  • 77.022 Lid closure labelled correctly with NetMap ID and facing upwards

  • 77.023 12mm micro duct carrying cable is correctly labelled with NetMap elements

  • 77.027 All microducts are labelled

  • 77.029 Joint bundle wrapped in Eziwrap or A3 - 250 micron clear plastic and secured

  • 77.042 Micro ducts 1 - 26 enter through 3 RH ports (viewed from swing arm)

  • 77.044 100mm duct capped at pole

  • 77.046 Minimum bend radius achieved inside pit (149mm for 116f, 110mm for 48f)

  • 77.051 Enclosure support bracket in place

  • 77.052 Tray retention strap in place

  • 77.061 Chamber lid secured

  • ABFFP photos

  • 77.064 Water ingress - no water access to closure

  • 77.065 End stops on all 5mm and 12mm tubes

  • End Cap Photos

  • 77.066 5mm divisible seals on all working trays

  • 77.067 Pressure testing completed

General Workmanship checks

6.000 Work Areas & Safety

  • 6.009 Joint chamber/manhole lid closed and secure

  • 6.014 Any defects to existing network outside of scope of project referred to be rectified in the future

  • 6.015 All power clearances maintained (underground and overground)

72.000 Reinstatement

  • 72.001 Properly damage made good

  • 72.014 Any road markings damaged by works are restored

  • 72.018 Ground reinstatement completed

  • 72.020 Surplus soil removed

  • 72.021 Reseal completed - footway / vehicle resurfaced

  • 72.028 Reinstatement completed to standard

73.000 Site tidy

  • 73.001 Site tidy, no task waste - poles

  • 73.024 Site tidy, no task waste - general

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.