Project Name:
Mascott QCC-Metal Decking
-
Sub-Contractor:
-
Relevant Drawing’s:-
-
Temporary works required (Please Indicate)
-
YesIf Yes Please attach Temp works sheet
-
Area/Location:
-
Sub-Contractor
-
Thickness of decking
-
Are top of contact services (beams) clean of paint and rust?
-
Fixings. Are sheets attached correctly?
-
Sheet overlap width
-
Are side laps correctly secured?
-
Are spans and ends of sheets correct?
Concreting
-
propping required
-
end/service openings closed?
-
check edge trim line and support?
-
studs welded as per drawing no -
-
mesh laid as per drawing
-
U bars tied to mesh
-
Expansion joint Fitted
-
Concrete Poured and finished to specification
The above works have been inspected and : -
-
Are to an acceptable standard of quality
-
Are to an acceptable standard of quality
-
Are to an acceptable standard of quality subject to the comments below
-
Are not to an acceptable standard of quality
-
Signed on Behalf of MCE
-
Date:
-
Signed on Behalf of Client :
-
Signed on Behalf of SubContractor :
-