Title Page
-
Site conducted
-
Floor
-
Block
-
Date
Communal Sign Off
-
Has our containment been completed in its entirety
-
Has all 1st fix power & lighting cabling been completed
-
Has all ELV cabling been completed to apartments
-
Has Non-combustible fixings been used
-
Are the lighting points installed to the correct positions
-
if applicable- are the detectors been installed to the correct locations
-
If applicable- has the apartments mains cables been installed
-
Has all our works been completed allowing close up of ceiling
Signiture
-
Signiture