Information
-
Contractor Company:
-
Client:
-
Job Name / Number:
-
Task Observed:
-
Location:
-
Conducted on:
-
Jobsite Supervisor:
-
Prepared by:
-
Personnel Onsite: (Head Count)
-
General (Click this tab for all Jobs)
-
Task Hazard Analysis
Task Hazard Analysis
-
Was a THA completed for all tasks being performed?
-
Does the contractor review the THA with all visitors to jobsite?
-
Are all hazards addressed on the THA?<br>
-
Are appropriate control measures in place for the hazards?
-
Have all employees signed the THA?
-
Are all tasks properly and identified on the THA?
-
Are all obstructions such as, overhead lines, or items unique to the jobsite identified on the THA?
-
Other.
-
Add Section Notes and Observations.
-
Mechanical Equipment
Mechanical Equipment (including, foreman/lineman trucks, bucket trucks, digger derrick, etc.)
-
Are safety belts worn while operating?
-
Is the equipment being used as intended?
-
Have pre-use inspections been completed on all equipment?
-
Are there any defects noted on the equipment inspection?
-
Is there an operators manual onboard?
-
Is the housekeeping inside of the equipment satisfactory?
-
Is all equipment in satisfactory condition?
-
Is there a fire extinguisher on equipment or available onsite? And properly tagged and in date?
-
Have all operators been trained in the operation of their equipment?
-
What is the condition of the tires? Do the tires meet DOT requirements? (Add a photo if condition is not satisfactory)
-
Has equipment been grounded where needed?
-
Is there a backup alarm on all equipment or is the contractor using a spotter?
-
Is the Die electric inspection current? (on equipment booms)
-
Is the DOT tag current?
-
Do the employees driving the equipment that requires a CDL; are their CDL valid? (Are the CDL and Medical on the person?)
-
Other
-
Add Section Notes and Observations.
-
Housekeeping
Housekeeping
-
Has the contractor addressed all housekeeping issues on jobsite?
-
Are flammable liquids properly stored?
-
Are flammable liquids properly labeled?
-
Are there any chemical spills?
-
Is the spill a hazardous chemical?
-
Other
-
Add Section Notes and Observations.
-
Personal Protective Equipment
Personal Protective Equipment
-
Are all employees wearing at a minimum a hardhat, safety glasses w/side shields, proper footwear, and proper safety vest?
-
Are all employees wearing work gloves appropriate for the hazard?
-
Are all employees wearing appropriate fall protection when required? Note: 100% fall protection is required while working at elevated heights.
-
Are all employees working on or near energized equipment outfitted and wearing FR clothing properly. ***IF NOT STOP WORK IMMEDIATELY***
-
Is PPE in good condition?
-
Are employees staying out of pinch / crush points (or the bite)?
-
Other
-
Add Section Notes and Observations.
-
Personal Protective Equipment
Weather Conditions:
-
Are mitigation measures for Heat Stress in place addressed and reviewed?
-
Is storm or severe weather preparedness and evacuations addressed during the THA meeting and noted?
-
Is their lightning near by? What is the distance?
-
Other
-
Add Section Notes and Observations.
-
Communications
Communications
-
Is a complete emergency plan documented and on site? Note: Plan shall include emergency contacts, map to local hospital and procedures to follow in the event of an emergency.
-
Has the plan been reviewed with all employees?
-
Is a copy of the safety manual on site?
-
Are SDS available to on site personnel?
-
Is an AED available? (Note the date of the last inspection)
-
Are adequate first aid supplies available on site?
-
Is there a Blood Borne Pathogen kit onsite?
-
Is a radio in use when flagging, pulling wire, etc. (or hand signals)
-
Has job site supervision completed OSHA 30hour training, including subcontractor employees?
-
Have all employees completed OSHA 10 hour training, including subcontractor employees?
-
Other
-
Add Section Notes and Observations.
-
Fall Protection
Fall Protection
-
Is 100% Fall Protection being observed while working at elevated heights? ****STOP ALL WORK IMMEDIATELY IF NOT****
-
Does each person working at elevated heights have the appropriated PFAS? ****STOP ALL WORK IF NOT****
-
Is the appropriate Anchorage point in use? (5000 lb requirement).
-
Is there a fall rescue/retrieval or means of fall rescue available kit onsite?
-
Is the fall protection in use in good condition?
-
Is the manual retrieval device available for excavation work? (Note the condition of the device)
-
Other
-
Add Section Notes and Observations.
-
Traffic Control
Traffic Control
-
Was traffic control in place prior to the crew beginning the work task?
-
If there is a road closure, is the proper closure, signage, detours, and sidewalks closed?
-
Are the workers properly protected from vehicle traffic?
-
Are all persons in the work zone wearing high visibility clothing?
-
Have all required permits been obtained for any public road crossings?
-
Have all road crossings been properly guarded?
-
Are all staying out of the work zone when not involved in the task?
-
Are spotters / flaggers being used at all times?
-
Are flaggers properly trained?
-
Are proper communication methods in use? (What form)?
-
Other
-
Add Section Notes and Observations.
-
Hand Tools
Hand Tools
-
Are hand tools in good working conditions (i.e. broken handles, etc.)?
-
Are ladders in good working condition?
-
Are GFCIs used on all electrical equipment? Are all power cords in good condition
-
Are all power hand tools in good working condition with appropriate guards?
-
Is the proper tool in use for the task?
-
Other
-
Add Section Notes and Observations.
-
Overhead Work
-
De-energized work (check box if this applies to the current job)
De-energized work
-
Is there a clearance on the line?
-
Does the Foreman know who holds the clearance, non-reclose order or hold order for the facilities being worked?
-
Has the transmission dispatch representative been contacted?
-
Has the line been tested and grounded?
-
Was there a flag installed on the grounds?
-
Has the crew elected to work as hot but de-energized?
-
IS the crew wearing rubber gloves and sleeves?
-
Do the Foreman and crew know and understand the clearance points?
-
NRO Number? (Where is this documented onsite?)
-
Other
-
Add Section Notes and Observations.
-
Working on or Near Energized Equipment (check box if this applies to the current job)
Working on or Near Energized Equipment
-
Is there a rescue kit on site or a hand line on the pole?
-
Are all employees maintaining minimum approach distances (MAD)?
-
Are all energized facilities covered or guarded to prevent contact? Including the line.
-
Has contractor been advised of equipment under an NRO order and have they logged in with Dispatch?
-
Are all employees working on or near energized equipment outfitted and wearing FR clothing properly. ***IF NOT STOP WORK IMMEDIATELY***
-
Other
-
Add Section Notes and Observations.
-
Are the employees working with transformers or regulators? (check box if this applies to the current job)
Transformers or regulators
-
Has the transformer been verified as PCB or non PCB?
-
Are the employees disposing of the transformers properly?
-
Grounding (check box if this applies to the current job)
Grounding
-
Have all lines and equipment been de- energized, tested, and grounded when required?
-
Have all sources of energy been considered including induced voltage?
-
Are powerline grounds being installed and removed properly (chain or parallel)?
-
Is equipotential grounding used?
-
Has the equipotential zone been barricaded, is the barricaded and maintained?
-
Are crews grounding the equipment?
-
Other
-
Add Section Notes and Observations.
-
Underground Work
Underground Work
-
Excavation (check box if this applies to the current job)
Excavation
-
Have locates been called, located, marked, and cleared?
-
Are the locates current?
-
Has an excavation competent person inspected the job site prior to entry each shift and when conditions change?
-
Document the soil type.
-
Are the spoils 2ft back from the trench or excavation's edge?
-
Are opened excavations & opened trench ways barricaded, or properly protected?
-
Is a ramp or ladder available when the trench is greater than 4ft in depth?
-
Is the ladder no more than 25ft from the work?
-
Is fall protection in place for excavations or pier holes (PFAS, with proper anchor point, guardrails or hole covers)?
-
Are excavations or trench’s made safe when unattended (is public protected from fall or cave in exposures)?
-
Other
-
Add Section Notes and Observations.
-
Hydro vac operations (check box if none apply to current job)
Hydro vac operations
-
Are the employees wearing rain or water protective suits?
-
Are the employees wearing face shields?
-
Are the employees wearing hearing protection?
-
Are dig permits up to date?
-
Are the employees using fall protection after 6ft depth is reached?
-
Are proper anchorage points in use (what form anchor point)?
-
Are hydro vac exactions barricaded / or protected to prevent employee or public access or falls.
-
Foundations
Foundations
-
Right-of-Way
-
Right of Way or Substation (check box if this applies to the current job)
Right of Way or Substation
-
Has the transmission dispatch or client representative been contacted prior to entering the substation?
-
Does the crew understand the easement delineation of the ROW?
-
Is the crew/crews staying on R.O.W.?
-
Does the crew understand the proper clearances from power lines?
-
Does contractor keep gates closed and locked?
-
Other
-
Add Section Notes and Observations.
-
Shop and Yard
Shop and Yard
-
Cranes (check box if this applies to the current job)
Cranes
-
Are safety belts worn while operating?
-
Is the crew involved in a critical lift?
-
Has a critical lift plan been competed prior to the lift?
-
Have pre-use inspections been completed on all equipment?
-
Is all equipment in satisfactory condition?
-
Is the housekeeping inside of the equipment satisfactory?
-
Is there a fire extinguisher on equipment or available onsite? And properly tagged and in date?
-
Is a signalman identified on the THA?
-
Have all operators and signalmen completed the required training for job position?
-
Has equipment been grounded where needed?
-
Are the outriggers fully extended, with proper outrigger pads and solid ground or surface?
-
Are employees staying out of the drop zone / line of fire (also known as the bite)?
-
-
Is there a backup alarm on all equipment or is the contractor using a spotter?
-
Is the crane and or swing radius barricaded properly?
-
Is the proper rigging in use?
-
Has the rigging been inspected with capacity tags intact / in place?
-
Other
-
Add Section Notes and Observations.
Notes of Obersavation: Please provide comments below:
-
Add site descriptive media to detail your site audit.
-
Add Section Notes and Observations.
Sign Off
-
Supervisor/s
-
Date:
-
Auditor/s
-
Date: