Information
-
PFS NEW STORE OPENING CHECKLIST
-
Site Name/Number
-
Store Manager:
-
Area Manager
-
PFS Operations Coordinator
1.Car wash.
-
1.1. Machine to current specification including under chassis wash.
-
1.2. Chemicals full and minimum level marked on containers.
-
1.3. Sound horn signage displayed in wash bay.
-
1.4. Silt trap clear.
-
1.5. Bay lights working.
-
1.6. Programmes working, all 3.
-
1.7. Heater in plant room and operational.
-
1.8. Plant room access clear.
-
1.9. Cat 5 cable fitted and terminated for future use.
-
1.10. EPOS Prices correct.
-
1.11. Car Wash Price poster displayed.
-
1.12. Daily checklist displayed on staff notice board and on the e-site register.
-
1.13. All ducts sealed in both wash bay and plant room.
-
1.14. Water softener installed and salt available.
2. Jet wash.
-
2.1. Working on all programmes.(7.5 minutes £3, 10 minutes £4, 12.5 minutes £5, 15 minutes £6).
-
2.2. Chemicals full.
-
2.3. Spare hose, lance and brush available.
-
2.4. Padlocks available.
-
2.5. Fitting tools left by contractor. (Adjustable spanners x2).
-
2.6. Daily check sheet displayed.
-
2.7. Prices correct on EPOS (7.5 minutes £3, 10 minutes £4, 12.5 minutes £5, 15 minutes £6).
-
2.8. Not linked to trend system.
-
2.9. Cat5 cable fitted and terminated for future use.
-
2.10. Correct decal fitted.
3. Vacuum.
-
3.1. Working and timer set correctly (£1.00 for 4 minutes).
-
3.2. Price correct on EPOS (£1 for 4 minutes).
-
3.3. Fragrance chemical full.
-
3.4. Spare crevice tool and hose available.
-
3.5. Cat5 cable fitted and terminated for future use.
-
3.6. Daily check sheet displayed.
-
3.7. Correct decal fitted.
4. Airline.
-
4.1. Working and timer set correctly
-
4.2. Free air button available on EPOS.
-
4.3. Caution legal sign fitted.
-
4.4. Cat5 cable fitted and terminated for future use.
-
4.6. Correct decal fitted.
5. Offset fill.
-
5.1. Vent stacks numbered correctly (to tank number).
-
5.2. Correct grade labels fitted.
-
5.3. Hazard warning signage fitted.
-
5.4. High level alarm signage fitted.
-
5.5. VR connection signage fitted.
-
5.6. 2 hose connection sign fitted.
-
5.7. Padlocks and keys available (universal DHL set).
-
5.8. Vapour balance warning signage fitted.
-
5.9. Slope on offset fill point towards interceptor.
-
5.10. Yellow hatching as per DSEAR - complete tanker bay - not applicable on dedicated tanker lane.
-
5.11. High level and low level lighting working and to specification, low level lighting ducting and cable on the external offset wall sealed.
6. Manholes.
-
6.1 Manhole lifter available.
-
6.2. Correct grade label fitted.
-
6.3. VR2 warning label in all unleaded chambers.
-
6.4. Pipe work labelled to pumps.
-
6.5. Check the valves are open/closed.
-
6.6. Security grates fitted within manhole chambers.
-
6.7. Lifters for security grates.
-
6.8. Brass padlocks used for security covers.
-
6.9. Vacuum testing complete by Berry's and documents filed on the s:drive.
-
6.10. Interstitial monitor fitted to all tanks.
-
6.11. Tank capacity to Morrison's specification/P2T.
7. Interceptors.
-
7.1. Check interceptor channels are complete and clear.
-
7.2. Interceptor grates fixed securley.
-
7.3. Interceptor manhole lid to be blue fibrelite.
-
7.4. Secure ducting sealed.
-
7.5. Interceptor pipe the correct height (2.4 meters) should not be brown and cowl fitted at the top.
-
7.6. Interceptor sensor visible on the tank gauge/wet stock provider to confirm prior to splash delivery.<br>
8. Pumps.
-
8.1. Verified and commissioned for fuel and VR2.<br>
-
8.2. Pumps working and prices correct.
-
8.3. Locking bars and padlocks available (including single locking bars).
-
8.4. VR2 label fitted.
-
8.5. Calling correctly to EPOS.
-
8.6. All signage fitted (numbers, operating instructions, Alvern, Magnecap, stanchion legal, m logo).
-
8.7. Pump bodywork and paint work (check for chips, scratches, build quality).
-
8.8. Pump level standing check with spirit level.
-
8.9. Out of order signage available (supplied by purchasing on expenses positive statement).
-
8.10. Labelling fitted under the pumps (pipework to tank matches as per P2T map).
-
8.11. Pumps according to Morrison's specification (global v5 pump).
-
8.12. Temperature compensation fitted and switched off for future use.
-
8.13. Grade orientation to Morrison's specification.
-
8.14. Hanging hose and not retraction.
9 LPG.
-
9.1. Correct pump installed (global v5 LPG).
-
9.2. Price correct.
-
9.3. Correct Point of Sale to specification and positioned correctly on pumps (pump number, LPG Operating instructions).
-
9.4. Divisor nozzle fitted with splasguard.
-
9.5. Padlock and keys available.
-
9.6. Individual locking bar supplied by Wayne.
-
9.7. Compound Cage padlocked and keys available (2 gates).
-
9.8. Lighting fitted emergency stop signage correct.
-
9.9. Hazard signage fitted to cage.
-
9.10. Two x 9kg dry powder extinguishers and boxes in cage.
-
9.11. Wayne emergency contact number signage fitted with correct details.
-
9.12. Tank capacity to Morrison's specification (refer to s:drive for clarification).
10. OPT's.
-
10.1. Working.
-
10.2. All fuel cards set up correctly (confirm with Fujitsu engineer).
-
10.3. Keys available (supplied by htec engineer).
-
10.4. Printer rolls full and spares available.
-
10.5. Header signage in place (marketing to arrange through signage fitter)...
11. Pole.
-
11.1. Three line display and built to specification (refer to specification manual located on the s:drive).
-
11.2. Fuel Prices correct (Petrol Pricing Manager to provide prices for all grades prior to opening).
-
11.3. Advertising in situ where applicable (marketing to arrange through signage fitter).
-
11.4. Separate on/off switch for turning off LED in kiosk are labelled and in the back office (standard switch clearly labelled).
12. DEC Box.
-
12.1. Keys available.
-
12.2. Telephone working.
-
12.3. Alarm working.
-
12.4. Fill point lights (high level and low level) activate when door is opened.
-
12.5. Pump 2 tank laminated map provided by Vianet displayed in the DEC box.
13. Fire Equipment.
-
13.1. Fire box, 1.x 6kg powder fire extinguisher and 1 x fire sand bucket with spreading implement.
-
13.2. Correct amount of extinguishers refer to as built drawings for clarification.
-
13.3. Sand buckets and spreading tool available.
-
13.4. Spare sand available.
-
13.5. Dry powder and CO2 extinguisher available in the kiosk - refer to as built drawings for location.
-
13.6. Contaminated sand container in situ padlocked, keys and contaminated bags available.
14. Cylinder Gas.
-
14.1 Training guide and bar codes supplied by Calor.
-
14.2. Cage as per drawing and drawing filed on the s:drive.
-
14.3. Door legal signage in place.
-
14.4. Padlock and keys available.
-
14.5. Cage full.
-
14.6. Calor RIsk Assessments completed and filed.
15. Legal signage.
-
15.1. Fireman's switch and electric switch fitted with correct signage.
-
15.2. Canopy height restrictions signage fitted.
-
15.3. Head office licence address signage to be fitted on the front of the kiosk.
16. Non legal signage.
-
16.1. Current posters displayed to include car wash and opening times.
-
16.2. Spare set of pump numbers and operating instructions.
-
16.3. Spare Alvern inserts supplied by marketing.
17. Back office.
-
17.1. All ducting sealed/electrical cupboard, UPS and by pass switch.
-
17.2. Notice board 4ft by 4ft back office and store room area.
-
17.3. E-Site register set up and documentation correct and in place.
-
17.4. Notice board set up and documentation in place.
-
17.5. Emergency pack set up.
-
17.6. File cabinet set up.
-
17.7. Pump 2 tank map.
-
17.8. Hazard zone drawing.
-
17.9. DSEAR complete, approved by forecourt operations manager, filed on the s:drive and tracker updated.
18. Site records - S drive
-
18.1. Filed on the S:drive:- tank test certificates, pipeline test certificates, chamber testing certificate, DSEAR, Hazard zone drawing, pump 2 tank mapping, and fm site set up document.
-
18.2. Update site details spreadsheet.
Ready to Trade: Forecourt set up, fuel prices correct on pumps pole sign, pumps primed , OPTs working, Valeting equipment working, PFS open signage displayed, tannoy working
Sign Off
-
PFS Operations Coordinator
-
Forecourt Operations Manager