Production Daily Checklist
Shift Start
-
Was adequate baling carried out during 5:00-7.30pm shift yesterday?
-
Was housekeeping carried out externally before end of yesterdays shift?
-
Did Production commence at 7am
-
Were all production staff at their stations ready to commence work at 7am
-
Was there sufficient quantise of broken bales in bays at start of shift
-
Had all bags of plastic, rubbish etc been removed from back of main conveyor the previous evening
-
Comments
Pre use checks on all balers, conveyors & forklifts
-
Were pre use checks carried out & recorded before 7am?
-
Name of person
-
Are all pre use checks carried out & recorded on picking line?
-
Name of person
-
Are all pre use checks carried out & recorded on baler & generator?
-
Name of person
-
Are all pre use checks carried out & recorded on Giant?
-
Name of person
-
Are all pre use checks carried out & recorded on Ken Mills baler?
-
Name of person
-
Are all pre use checks carried out & recorded on CK baler?
-
Name of person
-
Are all pre use checks carried out on all forklifts carried out & recorded?
-
Name of person & machine number
-
Name of person & machine number
-
Name of person & machine number
-
Name of person & machine number
-
Name of person & machine number
-
Have you signed as acknowledgement any issues raised on any sheet and applicable correctives actioned? Job sheets / proof of resolution should be stapled to specific sheet when closed out
Swan Neck
-
Are the two men at Swan Neck doing job properly:
-
All bags opened up
-
Are Colour & Rubbished being pulled out. If not comment
-
Comment
Picking Line
-
Are all line operatives picking materials correctly & not missing material. If not comment
-
Are recyclables being extracted. If not comment
-
Are they extracting all contaminants. If not comment
-
Are they placing materials in correct bags. If not comment
-
Is Film being placed in Rubbish bag. If Yes comments – action
-
Are all full bags being removed. If not comment
-
Is Dry Film being picked from line. If not comment
-
Is Clear Film being picked placed in colour bag. If not comment
-
Were there Gaps on Picking during the day
-
Check that E stop is not being activated by pickers
Connector Conveyor
-
Is last person on Conveyor ensuring that no contaminants drop into Baler. If not comment
-
Comments
Baler
-
Is there always someone at start of Baler Conveyor to ensure no contaminants especially wood, metal get as far as Bales
-
Have Dolav attached to Roller at end of connector been regularly checked & changed when needed?
Bale Quality Check
-
Are Bales coming out of machine of required quality with no visible contaminants. If not comment
-
Comments:
Dry Plastic picking from line
-
Is Dry Picker extracting all Dry Film from line. If not comment
-
Is Martis or machine operator extracting Dry Film from Baler Conveyor. If not comment
Stoppages
-
Did machine stop for any reason. If yes record reason & time start – time finished
-
Comments
Full Bags
-
Are all full bags removed & placed in storage bay. If not comment
-
Comments
Operation of line during breaks (Select N/A when not in use)
-
Did line continue seamlessly at first break 10am to 10:30 and second break 1:30pm to 2pm
-
Did giant operator at changeover start precisely at 10am and 2pm
-
Were all pickers at changeover in place at precisely 10am and 2pm
-
Overall did line & giant run uninterrupted from 9:30 to 10:30 and 1pm until 2pm
-
Were all staff properly deployed from 9:30 to 10:30 and 1pm until 2pm
-
Did production start at precisely 7am
-
Is material being pushed off connector on to floor – If yes is this because Swan Necker are not doing job properly ?
-
Comments:
Dry Film Sorters - Alex / Dorota - Colour Dry Sorters
-
Do they always have bags of Colour Film to sort
-
Do they always have empty bags
-
Are they achieving hourly target
Wash Film Sorters (if applicable)
-
Do they always have Bales to sort
-
Do they always have empty bags
-
Are full bags being taken away
-
Are hourly targets being met
-
Following sections must be completed daily
Hourly Data Requirements
-
Number of Bales produced from line including weights of bales broken at baler
-
Number of stoppages
-
Comments
H&S Checklist
-
Are staff using walkways to Exit & Enter
-
Are all walkways & Exits clear
-
Was PPE worn at all times by staff & visitors to site
-
Were all H&S measures met in all areas of site
-
Were all Forklift measures re loading & offloading met. If not give details
-
Were all trailers and containers offloaded in a safe manner
-
Did anyone smoke in any area of yard apart from designated smoking area? If yes give details
Fire Safety Checks
-
Is trip switch in canteen off
-
Was photo taken
-
Were all electrical appliances disconnected from sockets in both offices
-
Were all electrical appliances disconnected from all warehouse unit
-
Are all gates & doors securely closed at end of shift?
Forklift Protocol
-
Are Forklifts stopping if pedestrians walking nearby?
-
Are they being driven in reverse when moving bales, bags etc?
-
Are they being driven at the correct speed?
-
Are they sounding horns when driving around corners?
-
Are keys removed when stopped for more than 5 min?
-
Are seatbelts worn at all times?
-
Comments
Operation of Giant Loader
-
• No pedestrians are allowed in the area where Giant operates
• When Clamp Forklift is breaking Bales it cannot operate in the same area as Giant -
Are the above two points being observed at all times?
-
Comments
Storage of Bales
-
All Bales of materials in warehouse have to be stored/stacked according to Health & Safety Regulations and creating no Risk to Employees
-
Are all bales from Baler stored safely & correctly?
-
Are Fire Break Zones still in place – if NO must be rectified before finish shift
-
Are all incoming bales stored safely & correctly?
-
Comments
Baling from 5 to 7.30
-
Is someone baling during this time?
-
Comments
Breaking of bales
-
Are goggles being worn at all time by person breaking bales?
-
Is person breaking bales shielded at all times from Giant by the position of his forklift?
Miscellaneous
-
Were heat gun checks carried
-
Were these checks recorded
-
1st time
-
2nd time
-
Was grade all baler checked for Bypass
-
Is there enough supply of diesel?
-
Were cardboard moisture checks carried out?
-
Was anyone seen smoking in Yard. If yes give details
-
Comments
-
Is there enough supply of wire?
-
Was scrap wire baled
-
Is there diesel in generator?
-
Are doors of generator left open
-
Are there sufficient paper & washing substances in canteen & toilet
-
Was daily dairy filled in
-
undefined
Welfare / Housekeeping
-
Were toilets & canteen cleaned
-
Stocks of toilet paper, soap and hand towels checked
-
End of Shift Report
-
Have enough bales been broken during the shift to keep production at optimum performance?
-
Has production area been properly cleaned up
-
Have all full bags of Colour, Rubbish etc. removed by JCB and placed in storage area and empty bags to replace them ( this is to be done after 5:15 when place has been cleaned)
-
Is all loose plastic removed from production area between 5 -5:15
-
Do Dry sorter have bales & empty bags (if applicable)
-
Are full bags from Colour Dry sorter removed & replaced by empty ones (if applicable)
-
Do wash sorters ( if applicable ) have bales & empty bags
-
Are all electric appliances unplugged e.g. Radios
-
Does Generator have enough diesel for next day
-
Are materials being bales from 5 to 7:30 Provide list of materials to be baled
-
Performances of all employees on site. Did everyone carry out their duties to their maximum ability. Provide details & circumstances of these that you feel did not do so
-
Details of any incidents that occurred during the day that should be of interest and indeed concern to Brendan, Conor, Danny
-
Details of all employees who are absent due to sickness or approved holiday
-
Daily stock sheet updated daily
-
Provide a brief report about todays shift offering any views on any aspect of the production system that can be improved upon to make it more efficient
-
Was daily stock sheet for all materials on site updated & forwarded
Weekly Checklist
-
Was Compressor used to Blow Dust etc. from Fan on Baler
-
Were Conveyors checked and cleaned underneath for dirt and plastic
-
Were side plates taken off baler to gain access to Rams and cleaned out under correct LOTO procedure?
-
Have offices been cleaned and floors washed
-
Comment