Title Page

  • Site conducted

  • Date

  • Completed by

Production Daily Checklist

Shift Start

  • Was adequate baling carried out during 5:00-7.30pm shift yesterday?

  • Was housekeeping carried out externally before end of yesterdays shift?

  • Did Production commence at 7am

  • Were all production staff at their stations ready to commence work at 7am

  • Was there sufficient quantise of broken bales in bays at start of shift

  • Had all bags of plastic, rubbish etc been removed from back of main conveyor the previous evening

  • Comments

Pre use checks on all balers, conveyors & forklifts

  • Were pre use checks carried out & recorded before 7am?

  • Name of person

  • Are all pre use checks carried out & recorded on picking line?

  • Name of person

  • Are all pre use checks carried out & recorded on baler & generator?

  • Name of person

  • Are all pre use checks carried out & recorded on Giant?

  • Name of person

  • Are all pre use checks carried out & recorded on Ken Mills baler?

  • Name of person

  • Are all pre use checks carried out & recorded on CK baler?

  • Name of person

  • Are all pre use checks carried out on all forklifts carried out & recorded?

  • Name of person & machine number

  • Name of person & machine number

  • Name of person & machine number

  • Name of person & machine number

  • Name of person & machine number

  • Have you signed as acknowledgement any issues raised on any sheet and applicable correctives actioned? Job sheets / proof of resolution should be stapled to specific sheet when closed out

Swan Neck

  • Are the two men at Swan Neck doing job properly:

  • All bags opened up

  • Are Colour & Rubbished being pulled out. If not comment

  • Comment

Picking Line

  • Are all line operatives picking materials correctly & not missing material. If not comment

  • Are recyclables being extracted. If not comment

  • Are they extracting all contaminants. If not comment

  • Are they placing materials in correct bags. If not comment

  • Is Film being placed in Rubbish bag. If Yes comments – action

  • Are all full bags being removed. If not comment

  • Is Dry Film being picked from line. If not comment

  • Is Clear Film being picked placed in colour bag. If not comment

  • Were there Gaps on Picking during the day

  • Check that E stop is not being activated by pickers

Connector Conveyor

  • Is last person on Conveyor ensuring that no contaminants drop into Baler. If not comment

  • Comments

Baler

  • Is there always someone at start of Baler Conveyor to ensure no contaminants especially wood, metal get as far as Bales

  • Have Dolav attached to Roller at end of connector been regularly checked & changed when needed?

Bale Quality Check

  • Are Bales coming out of machine of required quality with no visible contaminants. If not comment

  • Comments:

Dry Plastic picking from line

  • Is Dry Picker extracting all Dry Film from line. If not comment

  • Is Martis or machine operator extracting Dry Film from Baler Conveyor. If not comment

Stoppages

  • Did machine stop for any reason. If yes record reason & time start – time finished

  • Comments

Full Bags

  • Are all full bags removed & placed in storage bay. If not comment

  • Comments

Operation of line during breaks (Select N/A when not in use)

  • Did line continue seamlessly at first break 10am to 10:30 and second break 1:30pm to 2pm

  • Did giant operator at changeover start precisely at 10am and 2pm

  • Were all pickers at changeover in place at precisely 10am and 2pm

  • Overall did line & giant run uninterrupted from 9:30 to 10:30 and 1pm until 2pm

  • Were all staff properly deployed from 9:30 to 10:30 and 1pm until 2pm

  • Did production start at precisely 7am

  • Is material being pushed off connector on to floor – If yes is this because Swan Necker are not doing job properly ?

  • Comments:

Dry Film Sorters - Alex / Dorota - Colour Dry Sorters

  • Do they always have bags of Colour Film to sort

  • Do they always have empty bags

  • Are they achieving hourly target

Wash Film Sorters (if applicable)

  • Do they always have Bales to sort

  • Do they always have empty bags

  • Are full bags being taken away

  • Are hourly targets being met

  • Following sections must be completed daily

Hourly Data Requirements

  • Number of Bales produced from line including weights of bales broken at baler

  • Number of stoppages

  • Comments

H&S Checklist

  • Are staff using walkways to Exit & Enter

  • Are all walkways & Exits clear

  • Was PPE worn at all times by staff & visitors to site

  • Were all H&S measures met in all areas of site

  • Were all Forklift measures re loading & offloading met. If not give details

  • Were all trailers and containers offloaded in a safe manner

  • Did anyone smoke in any area of yard apart from designated smoking area? If yes give details

Fire Safety Checks

  • Is trip switch in canteen off

  • Was photo taken

  • Were all electrical appliances disconnected from sockets in both offices

  • Were all electrical appliances disconnected from all warehouse unit

  • Are all gates & doors securely closed at end of shift?

Forklift Protocol

  • Are Forklifts stopping if pedestrians walking nearby?

  • Are they being driven in reverse when moving bales, bags etc?

  • Are they being driven at the correct speed?

  • Are they sounding horns when driving around corners?

  • Are keys removed when stopped for more than 5 min?

  • Are seatbelts worn at all times?

  • Comments

Operation of Giant Loader

  • • No pedestrians are allowed in the area where Giant operates
    • When Clamp Forklift is breaking Bales it cannot operate in the same area as Giant

  • Are the above two points being observed at all times?

  • Comments

Storage of Bales

  • All Bales of materials in warehouse have to be stored/stacked according to Health & Safety Regulations and creating no Risk to Employees

  • Are all bales from Baler stored safely & correctly?

  • Are Fire Break Zones still in place – if NO must be rectified before finish shift

  • Are all incoming bales stored safely & correctly?

  • Comments

Baling from 5 to 7.30

  • Is someone baling during this time?

  • Comments

Breaking of bales

  • Are goggles being worn at all time by person breaking bales?

  • Is person breaking bales shielded at all times from Giant by the position of his forklift?

Miscellaneous

  • Were heat gun checks carried

  • Were these checks recorded

  • 1st time

  • 2nd time

  • Was grade all baler checked for Bypass

  • Is there enough supply of diesel?

  • Were cardboard moisture checks carried out?

  • Was anyone seen smoking in Yard. If yes give details

  • Comments

  • Is there enough supply of wire?

  • Was scrap wire baled

  • Is there diesel in generator?

  • Are doors of generator left open

  • Are there sufficient paper & washing substances in canteen & toilet

  • Was daily dairy filled in

  • undefined

Welfare / Housekeeping

  • Were toilets & canteen cleaned

  • Stocks of toilet paper, soap and hand towels checked

End of Shift Report

  • Have enough bales been broken during the shift to keep production at optimum performance?

  • Has production area been properly cleaned up

  • Have all full bags of Colour, Rubbish etc. removed by JCB and placed in storage area and empty bags to replace them ( this is to be done after 5:15 when place has been cleaned)

  • Is all loose plastic removed from production area between 5 -5:15

  • Do Dry sorter have bales & empty bags (if applicable)

  • Are full bags from Colour Dry sorter removed & replaced by empty ones (if applicable)

  • Do wash sorters ( if applicable ) have bales & empty bags

  • Are all electric appliances unplugged e.g. Radios

  • Does Generator have enough diesel for next day

  • Are materials being bales from 5 to 7:30 Provide list of materials to be baled

  • Performances of all employees on site. Did everyone carry out their duties to their maximum ability. Provide details & circumstances of these that you feel did not do so

  • Details of any incidents that occurred during the day that should be of interest and indeed concern to Brendan, Conor, Danny

  • Details of all employees who are absent due to sickness or approved holiday

  • Daily stock sheet updated daily

  • Provide a brief report about todays shift offering any views on any aspect of the production system that can be improved upon to make it more efficient

  • Was daily stock sheet for all materials on site updated & forwarded

Weekly Checklist

  • Was Compressor used to Blow Dust etc. from Fan on Baler

  • Were Conveyors checked and cleaned underneath for dirt and plastic

  • Were side plates taken off baler to gain access to Rams and cleaned out under correct LOTO procedure?

  • Have offices been cleaned and floors washed

  • Comment

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.