Initial Requirements

  • Client's Health & Safety Specification in File

  • Notification Dept. of Labour - proof of delivery

  • Mandatory Agreement S37.2 with Client

  • Construction Permit on file

  • Permit number prominently displayed

  • Letter of Good Standing

  • Copy of the OHS Act and its Regulations

  • Organogram displayed and up-to-date - with Appointment references<br>- Rev numbers displayed with date revised

  • Approved Occupational Health and Safety Plan on file

  • Method Statements approved and available on file (where required)

  • Internal Audits conducted by SHE Officer, Regional SHE Coordinator or other parties

  • Occupational Health, Safety and Environmental Policy signed by CEO Displayed

  • Employee Register in place and up-to-date

  • All employees on site have valid Medical Clearance Certificates

  • Signage in place to instruct all visitors to report to Site Office<br>- Offices clearly demarcated and signage clearly displayed

Inductions & Task Safety Training

  • Are all employees inducted and received site specific safety rules

  • Subcontractor induction including all other persons

  • Vistors Induction

  • Safe work procedures in place and communicated to the relevant personnel in relation to their duties

  • Where employee moves to different tasks have additional safe work procedures been done

  • Job specific in-house training conducted i.e. Working at Heights

  • Are Planned task observations conducted and where deviations are detected; are amendments and retraining done

Registers

  • Register indicating the number of Plant, Equipment and Machinery on-site - numbers verified monthly

  • Incident/Accident register including Statistics

  • 3rd Party Accident Register

  • Bulk mixing plant register - maintenance and repair

  • Construction Plant/Vehicles by Driver/Operator

  • Demolition

  • Excavation

  • Fire Extinguishers

  • Hazardous Chemical Substance inventory

  • First Aid Box Contents

  • Lifting tackle (slings, chains, ropes, etc)

  • Material Hoist daily inspections

  • Material Hoist Maintenance Records

  • Portable Electrical Equipment

  • Personal Protective Equipment

  • Scaffolding Inspection

  • Temporary Works Inspection Results

  • Temporary Works Concrete Pour Authorisation

  • Temporary Works Removal Authorisation

  • Traffic Safety Officer Inspection Report

Appointments

  • Principal Contractor Appointment CR5(1)(k)

  • Contracts Manager Sect. 16(2)

  • Plant Manager Sect. 16(2)

  • Site Agent Non-statutory Sect. 16(2)

  • Construction Manager CR8(1)

  • Alternate Construction Manager CR8.1

  • Competent Person - Mechanical GMR2(1)

  • Assistant Construction Manager CR8(2)

  • Sub-ordinate Competent Person - Mechanical GMR2(7)

  • Occupational Health, Safety and Environmental Officer CR8(5)

  • Construction Supervisor CR8(7)

  • Assistant Construction Supervisor CR8(8)

  • Occupational Health and Safety Representative Sect 17

  • Scaffolding Supervisor CR16

  • Stacking Operations Supervisor GSR28

  • First Aider GSR03

  • Electrical Installation and Machinery Supervisor CR24(c)

  • Certified Blasting Operation Supervisor ER12

  • Bulk Mixing Plant Supervisor CR20(1)

  • Drivers and Operators - Authorised CR23(k)

  • Demolition Operation Supervisor CR14(1)

  • Fall Protection Plan Developer CR10(1)(a)

  • Excavation Operation Supervisor and Inspector CR13(1)(a)

  • Fire Equipment Inspector CR29(h)

  • Hazardous Chemical Substance Supervisor HCS Reg

  • Incident Investigator GAR09

  • Lifting Machinery Inspector DMR18(5)-(6)

  • Ladder Inspector GSR13(A)

  • Material Hoist Inspector CR19(8)(a)

  • Lifting Tackle Inspector DMR18(10)(e)

  • Material Hoist Inspector CR19(8)(a)

  • Portable Electrical Equipment Inspector EMR10

  • Risk Assessor CR9(1)

  • Contractor Appointment CR7(1)(c)(v)

  • Suspended Platforms Supervisor CR17(1)

  • Occupational Health, Safety and Environmental Committee Nominee Sect. 19(3)

  • Temporary Works Designer CR12(1) read with CR6(2)

  • Temporary Electrical Installations Controller CR24(c)

  • Temporary Works Inspector CR12(1)

  • Temporary Works Erector CR12(3)(a)

  • Traffic Safety Officer

  • Temporary Works Supervisor CR12(2)

Hazard Identification & Risk Assessment

  • Task Specific Hazard Identification and Risk Assessment Register CR9(1)

  • Task Specific Hazard Identification and Risk Assessment done CR9(1)

  • Hazard Identification and Risk Assessment Monitoring plan CR9(1)(d)

  • Documented methodology of risk evaluation CR9(1)(b)

  • HIRA communicated to employees and evidence kept thereof CR9(3)

  • Inform and discussed with Contractors CR9(4)

  • Reviewed after changes and/or incidents CR9(7)

Occupational Health, Safety and Environmental Committee Meetings

  • Monthly Meeting and records thereof Sect 19(4)

  • Monthly Meeting Attended by Site Agent and General Foreman

  • Occupational Health and Safety Representatives Reports tabled

  • Contractors attend monthly OHSE meetings

  • Monthly Internal & External Audits done and reviewed

  • Incident Tabled and Preventative measures taken

  • Monthly Contractor Audits reviewed

  • Meeting minutes endorsed by Contracts Manager and Construction Manager

Subcontractor Documentation

  • List of Contractors available (K7)

  • Sect 37(2) agreements signed for all Contractors

  • Contractor Appointment in place for all Contractors

  • All Contractors are in the possession of Letter of Good Standing (FEM & WCA)

  • All Contractors have a Occupational Health, Safety and Environmental Plan and this has been approved by the Construction Manager

  • All Contractors have received the portion of the Client's Occupational Health, Safety and Environmental Specification applicable to their scope of work

  • All Contractors have been audited monthly

  • Closure of findings raised during the monthly Contractor Audits are available for inspection

Incident Investigation

  • All reportable incidents reported and WCL2 forms available on file

  • All incidents investigated and incident reports available on file

  • Effective Corrective and Preventative steps taken to prevent recurrence

  • Annexure 1 reports available on file

  • There is a system in place to report near misses and these are investigated

  • Incident Alerts discussed with all employees following the incident - Toolbox talks

Excavations

  • Excavation is shored/braced or sloped back to prevent collapse

  • Excavation inspected daily before use

  • Safe access and egress is provided for all employees

  • Excavation inspected after rain or after blasting in the vicinity

  • Excavation barricaded, guarded or cordoned off

  • Excavation inspected after an unexpected fall of ground or damage

  • Lighting provided where needed

  • Adequate warning signs strategically placed

Traffic Management

  • Traffic Management Plan in place

  • Traffic signage adequate

  • Spacing and alignment between signs correct

  • Traffic regulating equipment in place

  • All equipment working as planned

  • Certificates of competence available for all personnel

  • Shifts in place

  • Communication and procedures working properly

  • Traffic configuration available and accurate

Construction Plant & Vehicles

  • Are all relevant persons in possession of the applicable Driver's license

  • Professional Driver's permit valid where applicable

  • All operators in possession the applicable Certificate of competence

  • No passengers on construction plant

  • Inspected daily by Operator/Driver

  • Auto acoustic revised device fitted

  • Amber working lights fitted when working in traffic

  • Maintained in good working order

  • Parked plant equipment in fully lowered position

  • Access to moving parts prevented where practical

  • How are defects detected addressed - to be discussed at SHE meeting minutes

General Storage & Housekeeping

  • Storage adequate, neat, tidy and under control

  • All stacking done safely

  • Safe storage of fuel

  • Fuel tanks bunded - fire precautions taken

  • Adequate fire fighting equipment and signage

  • Lifting tackle marked with maximum loads indicated

  • Lifting tackle load test certificate including shackles

Fire Precautions & Equipment

  • Fire extinguishers readily available

  • Smoking near flammable substances prohibited

  • Suitable visual signs for escape routes displayed

  • Fire equipment regularly serviced and safe for use

  • Personnel trained

First Aid

  • First Aiders qualified with valid certificates

  • First aiders name and number displayed

  • First aider boxes sufficient

  • Contents as per the list in the regulations

  • The first aid box neatly sorted and in a clean condition

  • Location of the box indicated

Personal Protective Equipment

  • Symbolic signs re PPE displayed

  • Required PPE worn on site

  • Employees refusing to wear PPE, stopped from working and corrective action taken

  • Employee instructed on the proper use of PPE and record retained thereof

  • PPE issued free of charge

  • A system implemented to reissue damaged and lost PPE

Public Safety & Emergency Preparedness

  • Perimeter fenced up - if applicable to work area

  • Signs "Report to office", etc. displayed

  • Appropriate emergency numbers available and displayed

  • Emergency procedures communicated

  • Danger signs displayed - excavation, roadworks, etc.

  • Access control and security in place - work area

  • Public walkways demarcated and safe for use

  • No intoxicated persons allowed at the workplace

  • Emergency plan reviewed at regular frequencies and fire drills conducted

Environmental Management

  • Waste control and removal system in place

  • Drip trays used for leaking equipment and plant

  • No-go areas/ nature features and trees left undisturbed

  • Dust control measures in place

  • List of hazardous materials on site and disposal method indicated

  • HCS material safety data sheets available and communicated to relevant employees

  • Drinking water available for all employees

  • Toilets clean and hygienic

  • Toilet paper provided in toilet and available

  • One or more toilets /30 employees

  • Water and soap available

Electrical Installation & Equipment

  • Certificate of compliance available for all electrical installations

  • Proof of Electrician's competency retained on file

  • Guard against electrical cable/equipment on site

  • Adequate protection against underground cables

  • Leads are safe and do not obstruct walkways

Ladders

  • Ladders comply with the requirement of the regulations

  • Ladders are long enough for the task

  • Ladders are secured to the top to prevent it from slipping

Working at Heights

  • Employees working on height have been trained and proof kept on file

  • Fall protection plan is developed and site specific

  • Fall protection plan is implemented and maintained

  • Medical Clearance certificates include working at heights

  • Equipment used are inspected, in a good condition and maintained

  • Scaffolding adequate as per the Regulations and Standards (SANS 10085)

  • Public access to scaffolding prevented

  • Signage strategically placed and as per the standard

On-site Laboratory

  • Adequate lighting

  • Adequate ventilation

  • All employees handling HCS informed and trained

  • Complies with Schedule D

  • HCS identified and a register kept

  • MSDS's available for all HCS

  • HCS safely stored

  • Sufficient toilets available with toilet paper and handwashing facilitites

Site Specific Items

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.