Title Page
-
Document No.
-
Audit Title
-
Client / Site
-
Conducted on
-
Location
-
Audited by
-
Project
-
Unit Number
-
Floor Level
-
Go to next section
Categories
-
Select a Category you wish to Audit
- Penetrations
- Stack Work
- Down-Pipes/ Balcony Outlets
- Risers - Water Services and Gas Services
- Rough-In - Water Services and Gas Services
- As Built and Documentation
- Fit-Off
- Final Inspection
- Handover
Penetrations
-
Is setout correct
-
Penetrations installed / cored
-
Select date
-
Add signature
Stack Work
-
Setout correct
-
Stack work
-
Stack work supported correctly
-
Stack work tested for leaks
-
Test plugs been removed from inspection openings
-
Inspection openings accessible (all glued)
-
Are air admittance valves installed and accessible
-
Tundish installed in agreed location
-
Penetrations sealed, fire rated and noted on schedule
-
Acoustic lagging installed
-
Stack work labelled
-
Stackwork inspected
-
Select date
-
Add signature
Down-Pipes / Balcony Outlets
-
Set out correct
-
Pipe work grades correct
-
Pipework supported correctly
-
Pipework tested for leaks (applicable if cast in slab)
-
Acoustic lagging installed
-
Penetrations see you, fire rated and noted on schedule
-
Select date
-
Add signature
Risers - Water Services and Gas Services
-
Set out correct
-
Pipe work supported correctly
-
Pipe work capped off for testing
-
Valves and meters installed and accessible
-
Pipework installed and tested to manufactures recommendations
-
What Was the Kpa
-
Penetrations sealed, fire rated and noted on schedule
-
Pipe work inspected
-
Select date
-
Add signature
Rough - In - Water Services and Gas Services
-
Set out correct
-
Pipework supported correctly
-
Pipework through stud work siliconed
-
Pipework checked for any cross overs
-
PEX joints checked open (visual)
-
Noggins installed for fit-off / not bowing at all
-
Pipework capped off for testing
-
Pipe work installed and tested to manufacturers recommendations
-
What is the Kpa
-
Penetrations sealed, fire rated and noted on schedule
-
Bath installed connected and protected
-
Pipe work inspected
-
Select date
-
Add signature
As Built Drawings and Documentation
-
As-built drawing complete
-
Fire rating schedule complete
-
Select date
-
Add signature
Fit Off
-
All valves fully on
-
All fixtures fitted off as per manufacturers instructions
-
All siliconing complete
-
Are all floor wastes/shower waste clean
-
Are all tap aerators clean from debris and not leaking
-
Water level in cistern set at right level
-
Write down Hot water delivery Temperature in degrees Celsius
-
Have all basin/sink traps been checked for leaks
-
Have all shower/bath spindles and shower Rose/bath outlet been silicon – sealed behind cover plate
-
Select date
-
Add signature
Final Inpection
-
Final plumbing inspection been carried out
-
Select date
-
Add signature
Handover
-
Unit variations complete
-
You need clean and free from rubbish
-
All defects and outstanding items complete
-
Final visual check
-
Select date
-
Add signature
-
If completed then goto next section
Sign Off
-
Sign off to be initialled and signed by
-
Select date
-
Add signature