Have the Point of Work Risk Assessments been done for the day? (Add in brief description of the works being done on the day of the inspection)
-
Have all representatives that form part of the inspection been inducted incl. the lead auditor?
Plant Documentation
-
Which plant are in use for the day? (Brief overview of which plant and machinery are in use)
-
Spot check some of the plant (Check driver/operator competencies, lifting certificates, daily/weekly/monthly inspections etc.)
Emergency Documentation
-
Have all staff been briefed on the emergency procedure and arrangements for the site?
-
Is there a copy of the ERP available and are emergency contact numbers displayed in the site office?
Permits/GATW
-
Are permits to work/GATW's available for the work being carried out on the day of the inspection?
-
Have permits/GATW's been signed by the PC and do they have valid dates?
RAMS
-
Spot check a task for the day with the risk assessment and method statement submitted
-
Is the task being carried out safely and as per the risk assessment?
Site Inspection
Welfare
-
Suitable welfare in place for personnel and visitors? (Check running water, flushable toilets, drying rooms etc.)
-
Are welfare facilities in good condition and clean/tidy?
Store rooms/Containers
-
Are store rooms and containers clearly marked with which type of store it is? e.g COSHH, General, Liftin Equipment etc.
-
Are they clean/tidy with good housekeeping practiced? Everything has a place and everything is in it's place?
-
Are store rooms easily accessible with steps or are there any tripping hazards present accessing the container?
-
Are doors wedged open safely?
Excavations
-
Are excavations barricaded safely and sufficiently?
-
Are signage displayed where excavations are present?
-
Are any excavations filled with water? If so, is it from recent rain/drainage (ask the contractor why the excavation is filled)
-
Are deep excavations shored or sloped where necessary?
-
Are plant/machinery working too close to the edge of excavations? (While persons are working inside the excavations)
-
Are too many personnel working inside the excavations?
-
Do personnel have safe means of access into and out of the excavation?
Security/Access/Egress
-
Is the site suitable fenced off with applicable warning signs posted?
-
Are all persons signed in and out at the security entrance?
-
Pedestrian walkways clearly marked and identified? Are they safe and well established?
-
Designated parking area available and are persons reverse parking?
Working at heights
-
Are there any working at heights currently taking place
-
Are all persons working at height wearing the appropriate fall arrest equipment?
-
Have the fall arrest equipment been inspected?
-
Spot check a staff member regarding knowledge of working at heights and what procedures are in place.
Personal Protective Equipment
-
Are all staff and visitors wearing the appropriate PPE
-
Are personnel wearing the right PPE for the tasks they are performing
Plant & Machinery
-
Are plant in good and safe working condition?
-
Do plant and machinery not in use have plant nappies/drip trays stored underneath?