Title Page

  • Crew

  • Conducted on

  • Prepared by

  • Location
  • Ten Commandments of cavity wall installation

    1. Introduce yourself to the customer; be polite and professional.
    2. Carry out all pre-installation checks and inform them to remove all breakables from the exterior walls and window sills and check all walls for single skin.
    3. Ensure you have checked all heating appliances and ventilation requirements.
    4. Complete the material flow rate tests.
    5. Carry out the installation to KIWA BDA specifications and adhere to all health and safety requirements.
    6. Carry out the post installation checks.
    7. Ensure you have checked all heating appliances and ventilation requirements.
    8. Clean up all dust, remove all debris and wash down.
    9. Complete all paperwork including the customer care form and ask customer to sign, leave a copy of the flue check sheet.
    10. Ask the customer to inspect the work before you leave.
    Treat them and their property with respect

    This will help you deliver the service the customer is expecting from you and your company

  • The purpose of this checklist is to enable each team to complete their installs in an efficient and timely manner, ensuring that both team members are fully aware of their roles, responsibilities and duties to be completed to install the cavity wall insulation efficiently

  • Crew Leader

  • Crew Assistant

  • Select Role

  • Pre-Installation

  • Contact Client before arrival (onsite parking, Site Preparation, Special Requirements, ETA)

  • 5 Min

  • |Check Survey/ iAuditor

  • 5 Min

  • Introduction to the Client (advise client on work requirements)

  • 5 Min

  • Complete pre-checks

  • 10 Min

  • Installation

  • Drill 100% of furthest elevation (fit barrier brush)

  • 15 Min

  • Prepare mix (Colour Match)

  • 10 Min

  • Complete drill pattern

  • 30 Min

  • Install using second pipe (pointing holes whilst filling)

  • 20 Min

  • Post Installation

  • Complete Post works Checks

  • 10 Min

  • Complete Final Checks (Property Finish, Client satisfaction)

  • 10 Min

  • Pre-Installation

  • Health & Safety set up (Move Obstructions i:e Plants Pots)

  • 10min

  • Prepare Site ( Ladder set up, Drill ready, brush equipment)

  • 10min

  • Set up injection pipes ( Correct length, Calibration)

  • 10min

  • Installation

  • Commence Install (Pointing holes whilst filling)

  • 40min

  • Post Installation

  • Once install complete return equipment to vehicle ( Organisation)

  • 10min

  • Start Clean up process

  • 10min

  • Replace all movable obstructions to their original positions

  • 5min

  • Final Checks (All equipment accounted for, Property finish, Cleanliness)

  • 5min

Sign off

  • Sign below to confirm you understand the content of the audit and you will conform to its content whilst working on site.

  • Crew leader

  • Crew Assistant

  • Inspector

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.