Title Page

Pre-inspection preparation:

  • Pollution incident risk assessment (PIRA). The PIRA must be updated as part of the inspection. It can be completed before or after the visit. When updating the PIRA, take into account any environmental records on Sphera from the previous year and also findings from the environmental inspection. Speak to the Environmental manager or Degree Apprentice for instructions on how to update the PIRA if you are unsure.

  • If the operational site is being operated & maintained by an external contractor (GE, SGRE, Enercon, Wartsila are all examples) Contact them in advance of the visit to obtain: evidence of environmental spill response training and evidence of waste management (if this is in their contract to manage). Examples include certificates of completion for training, material used to deliver training and waste management paperwork.

  • Operational site name and location

  • Date the environmental inspection was conducted on.

  • People completing or participating in the inspection:

  • Has there been any Sphera Environmental Records since the previous inspection. If so, do they need to be reviewed during this check?

Planning and consents:

  • Has the 'operational sites compliance matrix' been changed to reflect current activity relating to planning commitments? Please summarise.

  • Does the site have active habitat/landscape and/or ornithological monitoring?

  • Please tick all monitoring that applies:

  • Out of the above list can any be practically assessed on site and/or via desk review? If an assessment can take place, summarise findings here.

Control building:

Solvents and Chemicals (PV Cleaner and Paints)

  • Are there any solvents/chemicals stored on-site. (Usually store inside of a shipping container or COSHH Locker)

  • If so, are all solvents and/or chemicals being stored appropriately and in good condition?

  • Describe any solvents or chemicals found and attach a photograph. e.g. includes panel cleaning solutions and paints. Type N/A if there are none present.

Waste:

  • Is there any waste storage facilities on site?

  • If so, are the waste storage facilities in good condition?

  • Is there any evidence of waste/spare panels on site?

F-gas:

  • is there an air conditioning unit at the control building? If so list all units and take photos of their specification stickers.

  • If applicable, have units been inspected in line with F-gas regulations?

  • Does the operational site have SF6 located in switchegear?

  • If the above question is yes, has the site's SF6 register been completed along with required leak tests?

Operational site surroundings water: pollution and/or silt risk:

  • Is drainage present that would pose a pollution risk?

  • If drainage is present, identify the best means of environmental risk reduction: identifying surface/foul vs. full drainage plan; drain covers on site are examples.

  • Are chemical & oil stores controlled in a manner to prevent pathways to drains? If 'no' then utilise the next section to make improvements & suggestions.

  • If there is no drainage plan, would the operational site benefit from one?

  • If applicable, is the drainage plan visible and easily accessed?

  • Watercourses: If practical, check for presence of silt. If silt is present, assess potential root causes, identify location on the printed map and take a photograph. Depending on circumstances this may be Sphera recordable.

  • Please describe here any concerns on the operational site regarding water pollution risk. (e.g. blocked culverts). If there is no specific concern, write not applicable.

Operational site surroundings: soil/unmade ground pollution risk / exterior check of assets

Environmental near hits & incidents:

  • Pollutant that has escaped containment (e.g. transformer) but not entered the environment (soil/water).

  • Pollutant that has escaped into the environment to soil. Example: Stains/liquids present on the soil/ground.

  • Pollutant that has escaped into the environment to watercourse. Example: Discolouration of the watercourse (that can be practically accessed).

  • Waste that has escaped into the environment (e.g. litter).

  • Deliberate fly tipping

  • Plant die back due/likely due to presence of pollution.

  • Evidence of fires (black patches on soil, items that have been burnt)

  • Dead wildlife, marine life, archaeological concerns present.

  • Is there any evidence of damage to the panels or connecting infrastructure on site?

Transformer Inspection

  • Enter the number of Transformers present on site

  • Make sure to sample at least 10% of the transformers on site and answer the following questions.

  • Are the sampled transformer(s) in good condition?

  • Are the sampled transformer(s) housed correctly? If they do not have housing consider whether it is necessary based on pollution risk and water ingress.

  • Is any evidence of damage to the transformer/housing of the transformer?

Environmental Inspection Summary

  • Please summarise the environmental inspection and include any findings not identified in the checklist items.

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.