Overhead Cabling Quality Audit
-
Is the cable at the correct height? Take photos to demonstrate.
-
Is a tree guard on ULW? Take photos to demonstrate
-
Cornering CBT correct stand offs? Take photos to demonstrate
-
Are the CBTs labelled and cable labelled? Take photos to demonstrate
-
Is the cable 50mm away from steps? Take photos to demonstrate
-
Has the correct aluminium strip and bonding nails with washers been used? Take photos to demonstrate
-
Are aluminium strips 450mm apart? Take photos to demonstrate
-
Is the cable dressed down the pole ladder loop between 1st and 2nd step, or down the middle of the pole? Take photos to demonstrate
-
Is the ELM 750mm from the bottom step? Take photos to demonstrate
-
ELM 2x coil on top, 3x coil on bottom? Take photos to demonstrate
-
Ensure the galvanised capping is not encroaching on pole markings. Take photos to demonstrate
-
Are there bonding nails on the galvanised capping, and bonding nails and washers on plastic capping? Take photos to demonstrate
-
Are all 4 holes used, with bonding nails, on the elephants foot? Take photos to demonstrate
-
Are fibre joints 750mm from the bottom step? Take photos to demonstrate
-
Is the cable loop 2m minimum form the ground? Take photos to demonstrate
-
Is there the correct bend radius from the CBT? Take photos to demonstrate
-
Sign to verify this audit.