  • In addition to checking the items in this template, items to constantly observe during crane usage:
    - All operating mechanisms are functional and free from maladjustment
    - Load is rigged properly
    - Hoist brakes checked each time a load approaching the rated load is handled

Pre-operation

  • Crane is registered and permitted to be used in operations

  • Operator is in good condition and is competent to perform the work

  • Operating and emergency controls are in place

  • Operator knows where the crane disconnect switch is located

  • There are no warning signs on or near the push button pendant or controls

  • There are no people working on the crane or in the runway travel area

  • There are no people working in the area, that the load the operator is going to pick up will travel

  • The area where the operator will set the load down is large enough and/ or cleared of obstructions

Equipment

  • Bridge

  • Motor

  • Brake

  • Shaft Couplings

  • Shaft Bearings

  • Gears

  • Wheels

  • Girders and Connections

  • Guards and Covers

  • Bumpers

  • Bumper Bolts

  • Master Switches

  • Pushbutton

  • Wiring

Main Hoist

  • Motor

  • Brake

  • Couplings

  • Gears, Shaft and Bearings

  • Upper Block

  • Lower Block

  • Hook, Magnetic Particle

  • Hook and Throat Opening Measurement

  • Hook

  • Hoist Cable

  • Rope Drum

  • Guards

  • Limit Switch

  • Cable attachment to drum

Trolley

  • Motor

  • Brake

  • Couplings

  • Gears, Shaft and Bearings

  • Frame

  • Wheels

  • Bumpers

  • Guards

  • Rails

  • Conductors

  • Collectors

Runways

  • Rails Including Span

  • Rail Joints

  • Main Conductors

  • Main Collectors

  • Inspection Copy and Date

  • Authorized User Sign

  • Lubrication

  • Capacity Signs

  • Warning Signs

  • Lockout Mechanism

Attaching The Load

  • Operator has done proper rigging and hoisting techniques

  • Hoist chain or hoist rope is free of kinks or twists and not wrapped around the load

  • Load is attached to the load block hook by means of slings or other approved devices

  • The sling cleared all obstacles

Moving The Load

  • Load is well secured and properly balanced in the sling or lifting device before it is lifted more than a few inches

  • Before starting the hoist, the hoist rope is not kinked and the multiple part lines should not be twisted around each other

  • The hook is brought over the load in such a manner as to prevent swinging.

  • No sudden acceleration or deceleration of the moving load was observed

  • Load is not in contact to any obstructions.

  • Hoisting, lowering and traveling is not being done when employees are on the load or hook

  • The operator tested the brakes each time a load approaching the rated load is handled. The brakes are tested by raising the load a few inches and applying the brakes.<br>

Recommendations

  • Write recommendations here

Completion

  • Full Name and Signature of Inspector

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.