Information

  • Document No.

  • Audit Title

  • Client / Site

  • Conducted on

  • Prepared by

  • Location
  • Personnel

  • Region

  • Contractors

  • Audit Date

  • Time

  • Audit Title

  • LIS No.

  • Equipment No.

  • Notification No.

  • Order No.

  • Date field works were completed

  • Construction Type

  • Voltages

1. LV Crossarm

  • Are cross arm level and size correct?

  • Have phase plates been fitted?

  • Has a N plate been fitted?

  • Have conductor clearances been maintained?

  • Are bridges neat and tidy?

  • Are conductors tied in and secured appropriately?

  • Has the public light been fitted appropriately?

  • Are assets built to approved design standards?

  • Have LV insulators been changed?

  • Are service tails or pole box leads adequately supported by under arm brackets?

  • Has the switchwire been removed?

  • If the switchwire has been removed has the remaining conductor been terminated correctly.

2. Services

  • Have all non standard services been changed as per opportunistic maintenance guidelines?

  • Are service heights compliant to requirements?

  • Do services have "N" tags ?

  • Are services terminated to standard requirements?

3. Hardware

  • Have line and PG clamps been replaced with Ampact connections where applicable?

  • Have all obsolete service clamps been removed from conductor?

  • Have obsolete or unapproved pole boxes been removed?

  • Are the newly installed materials approved?

  • Has opportunisitc maintenance been performed?

4. HV Crossarm

  • Are cross arm level and size correct?

  • Have phase plates been fitted?

  • Have conductor clearances been maintained?

  • Are bridges neat and tidy?

  • Are conductors tied in and secured appropriately?

  • Are assets built to approved design standards?

  • Have HV insulators been changed?

5. Sub T Crossarm

  • Are cross arm level and size correct?

  • Have conductor clearances been maintained?

  • Are bridges neat and tidy?

  • Are conductors tied in and secured appropriately?

  • Are assets built to approved drawings?

  • Have Sub T insulators been changed?

6. Pole

  • Construction Type

  • Has pole been sunk to required depth?

  • Is the pole straight?

  • Are appropiate labels been installed on the pole, eg LIS?

  • Has the correct amount of back fill and topsoil been used?

  • If a stay is attached is it at the correct angle, and constructed as per requirements?

7. Transformer

  • Has the transformer been built to UE design standards?

  • Has correct phasing identifaction been performed?

  • Have Surge diverters been replaced, and attached as per standard?

  • Have HV fuse units been replaced, and attached as per standard?

  • Has the structure had animal proofing installed as per the standard?

  • Have the LV leads been upgraded to the correct standard?

  • Have the HV leads been upgraded to the correct standard?

  • Has the TX been animal proofed to UE standard?

  • Have LV isolators been installed and to the correct standard ?

  • Are the dressing down insulators preferred items. i.e. not wine glass ?

  • Is the installed TX height complaint?

8. Worksite

  • Has the worksite been left clean and tidy?

  • Has vegetation been cleared to meet compliance?

9. SAP Claims

  • Does the SAP claim match the works conducted on site?

  • Does the service provider claims match the claims in UE SAP?

  • Comments

  • Overall Audit Rating

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.