Information
-
Document No.
-
Audit Title
-
Client / Site
-
Conducted on
-
Prepared by
-
Location
-
Personnel
Site OH&S
-
Has Safe Work Method Statement been left on site and signed by all employees/contractors?
-
We're all leads and tools that were used on site tested and tagged?
-
Has all left over paint and materials been stored neatly in designated area?
-
Has site been left clean/tidy and all rubbish removed?
Products, Colours and Materials.
-
Have all the products and materials been applied according to the finishes schedule?
-
Are all the colours correct and been applied according to the colour schedule?
Ceilings
-
Has the product been checked for coverage & consistency in all areas?
-
Have ceilings been backrolled?
-
Are there any visible cracks, joins, defects or filling required?
-
Is the stipple of the paint finish acceptable?
-
Is there any paint on light fittings or other items?
-
General notes on finish of ceilings.
Walls
-
Has the product been checked for coverage & consistency in all areas?
-
Are there any visible cracks, joins, defects or filling required?
-
Is the stipple of the paint finish acceptable?
-
Is the cutting in to the ceilings straight, neat and with no over painting?
-
General notes on finish of the walls.
Trim & Woodwork
-
Has the product been checked for coverage & consistency in all areas?
-
Are there any visible cracks, mitres, runs, defects or filling required?
-
Is the cutting in to the walls straight, neat and with no over painting?
-
Is the level of finish to all areas free from unacceptable brush marks?
-
Doors been painted top and bottom edges?
-
General notes on finish to trim.
External
-
Has the front step been oiled?
-
Have the lintels been painted and free from defects?
-
Have the eaves been painted and free from defects?
-
Has the spouting been painted and free from defects?
-
Has the fascia been painted and free from any defects?
-
Have the Weatherboards been painted and free from any defects?
-
Has the cladding been painted and free from any defects?
-
Have all external ceilings been painted and free from any defects?
-
Has the steelwork been painted and free from any defects?
-
Has the external doors been painted and free from any defects (including top and bottom edges)?
-
Has the front door been painted and free from any defects (including top and bottom edges)?
-
Have the external windows been painted and free from any defects (including paint on glass/aluminum/window furniture)?
-
Has the meter box been painted and free from any defects?
-
Has the stink pipe been painted and free from any defects?
-
Has the roof been painted and free from any defects?
-
Have the downpipes been painted and free from any defects?
-
Have rendered areas been painted and free from any defects?
-
Has the brickwork been painted and free from any defects?
-
Has the decking been painted/stained/oiled and free from any defects?
-
Have all fences and gates been painted and free from any defects?
General Notes
-
Are all areas free from paint splatter, over painting and all non painted times clean?
-
All items that have been removed; hinges, handles, door/window furniture and other items been reinstalled?
-
Are there any incomplete items or works?
-
General notes?
-
Signed by person completing inspection
-
Signed by Builder/Site Foreman
-
Signed by client
-
Signed by Painter