1. Project Manager Checklist
-
1.1 is there a signed safety policy with appropriate company policies in place?<br><br>
-
1.2 have you made all P&R operatives aware of their location? Signage recorded?
-
1.3 do you have adequate facilities to maintain paperwork & safety store materials on site?
-
1.4 is the Platt and Reilly training matrix in place & live?
-
1.5 Are toilet & canteen facilities adequate with supply of drinking & hot water?
-
1.6. Are CSCS training records copied & attached to Induction forms?
-
-
1.7. Have all P&R operatives been safety inducted by Platt & Reilly & the Principal Contractor?
-
-
1.8. Are all method statements live and have been communicated with signage recorded?<br>
-
1.9. Is there a requirement to prepare Method Statements? (If so Contact Martin Now)
-
2.0. Have accidents taken place?<br>
-
2.1. Have they been investigated & forwarded to head office?
-
2.2. Are Project Access arrangements Adequate?
-
2.3. Are there physical hazards? Give details & attach photos.
-
2.4. Are working at height arrangements adequate? Certificates in place & current?
-
2.5. Are GA2 / GA3 records Complete?
-
2.6. Are Manual handling arrangements Adequate?
-
2.7. Are Mechanical handling arrangements Adequate?
-
2.8. Are Housekeeping arrangements Adequate?
-
2.9. Are temporary lighting / power supply arrangements adequate?
-
3.0. Are there trained first aiders & first aid kits? Are your Team aware of this?
-
3.1. Are all employees wearing appropriate PPE? Have you recorded every item issued?
-
3.2. Are emergency procedures in place?
-
3.3. Are previous site safety inspection records complete & signed by you?
-
3.4. Is safety signage adequate?
-
3.5. Are security arrangements adequate?
-
3.6. Is the site fully enclosed?
-
3.7. Are Toolbox talks taking place with subject literature attached?
-
3.8. Is there a requirement to provide a safety representative?
-
3.8 ANY OTHER ISSUES??