Title Page
-
Site conducted
-
Conducted on
-
Prepared by
-
Serial Number
-
Asset Number
-
Vessel Type
-
Customer
-
Photograph
Vessel
-
Outer Vessel Condition
-
Outer Vessel Paintwork
-
Outer Vessel Welding
-
Outer Vessel Attachments
Frame
-
Frame Condition
-
Frame Paintwork
-
Frame Welding
-
Fork Lift Pockets
-
Roof Plates
-
Earthing Boss
-
Earthing Points Un Painted
-
Has the tie down bars been painted white APAC tanks only?
-
Sling Number
-
Ensure slings are sitting inside the IMO (below level of corner castings)
Pipe Work
-
Condition
-
To identify any open ended pipework located in the drip tray
-
Drip Trays
-
Relief Valves/Tags
-
Are relief valves pointing away from the tank
-
Cryofleet tanks to have x2 brass elbows fitted
-
Valves
-
End Caps
-
Check Gauges & Record Pressure / Contents
-
DP Gauge to have Cryofleet sticker on
-
Has pressure gauge cap expansion nipple been removed
-
Check & Ensure Travelling Valve is Open
-
Final inspection to external pipework - Non return valves are in correct direction
-
Final inspection to external pipework - Relief Valves are correct pressure and fitted correctly
-
For C02 vessels Non-return valve has been removed, identified and stored in a safe location. Identification to include customers details and date stored.
-
For 40ft tanks only - Has the 5- valve instrument manifold been fitted in the correct orientation
-
V6 valve for maximum efficiency only open ½ - 1 full turn max
Data Plates
-
DNV / EN
-
ADR / RID / IMO
-
CSC
-
ASME
-
PED
Decals
-
Regulations
-
Maximum Gross Weight
-
Tare Weight
-
Capacity
-
Schematic
-
Filling Ratio
-
Cryopacks to not have 12K7 decals fitted
-
ISO Packs to have x4 12K7 decals on each side
-
Asset Number
-
Are all 4 tie down point stickers attached
-
Is the BIC code on the rear of the tank (top of the frame) and side of the tank (vaporiser side) 2nd bracing from the top?
-
WCLU Numbers
Other
-
Document Holder
-
Cabinet
-
Manway
-
Rubber Lining Outer Vessel
Signatures
-
Inspected By
-
Date
-
Faults Acknowledged By
-
Re-Work Inspection By