Information

  • Audit Title

  • Document No.

  • Conducted on

  • Piling Rig

  • Contract + No.

  • Personnel/Site Operatives

  • Location
  • Prepared by

A: SITE ACCOMODATION & WELFARE

  • 1. Walkways wide enough for persons/mat.

  • 2. Are suitable rest areas provoded.

  • 3. Are food eating/heated areas provided.

  • 4. Is there facilities for drying/changing clothes.

B: SAFE PLACE OF WORK

  • 1. Is a safe means of access/egress provided.

  • 2. Is work area firm, level & suitable.

  • 3. Working areas free of obstruction.

  • 4. Is the required clear working area available.

  • 5. Is a rig exclusion zone in operation (20m >).

  • 6. Is the working area tidy (Housekeeping.

C: ACCESS/EGRESS TO AND FROM WORKPLACE

  • 1. Walkways wide enough for persons/mat.

  • 2. Are all access areas clear.

  • 3. Are all egress areas clear.

D: SITE ACCESS & TRAFFIC ROUTES

  • 1. Is the site entrance clearly signed.

  • 2. Is access free of over/under services.

  • 3. Are all traffic routes signed.

  • 4. Are vehicles & pedestrians segregated.

  • 5. Can vehicles turn where required.

E: GENERAL ITEMS

  • 1. Any overhead cables in piling area.

  • 2. Any underground services in piling area.

  • 3. If yes to above are they signed and marked.

  • 4. Has 'outage' or removal been arranged. 1 & 2

  • 5. Any ground contamination.

F: STORAGE & MOVEMENT OF MATERIAL

  • 1. Are compress gases stored/secured correctly.

  • 2. Are warning signs displayed.

  • 3. Are the required fire extinguishers available.

  • 4. Is hard standing available for pile storage.

G: PPE - PERSONAL PROTECTIVE EQUIPMENT (Is correct PPE in use)

  • Head

  • Ear

  • Hand

  • Foot

  • Body

  • Eye

  • Other Items

H: RIG / FOREMAN DOCUMENTATION

  • 1. Daily / Weekly Plant Inspection Checklist completed.

  • 2. Accident book - any unrecorded items.

  • 3. Foreman's Health & Safety Pack in order.

  • 4. Six monthly rig/tackle examination complete.

  • 5. Operations manual on site ( Foreman & Topman) & in-date.

  • 6. Piling platform certificate completed & available.

  • 7. Permit to PIle completed & available.

  • 8. Foremans Safety Audit Completed.

  • 9. Toolbox Talks completed.

J: RIG EQUIPMENT

  • 1. Safety harness available & in order.

  • 2. Safety lanyard available & in order.

  • 3. Karabina or links available in order.

  • 4. Ladsaf fall arrest gear in order.

  • 5. Ladder Serviceable & undamaged.

  • 6. First Aid kit in order.

  • 7. Fire Extinguisher in order.

  • 8. Spill Kit(s) available on site & full.

  • 9. Hose carrier/bund on site.

  • 10. Trailer ladder(s) in order.

  • 11. Trailer bracket(s) in order.

  • 12. Extension Ladder(s) in order.

  • 13. Diesel Tank/IBC Tested & Lifting Sling in-date (No Damage)

K: CONTRACT DOCUMENTATION

  • 1. Risk assessment - job specific.

  • 2. Method Statement - job specific.

  • 3. Contract Instruction sheet available.

L: PILING RIG AND EQUIPMENT MAINTENANCE

  • Any maintenance related issues?

  • Comments:

  • Foreman:

  • Auditor:

  • Select date

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.