Title Page
Audit Details
-
Photo of the work activity
-
Select date
Permit To Work Details
-
Permit Serial Number
-
Contractor Company Name
General Permit Information
-
Is the company name correct ?
-
Are the authorised person and issuer the same person ?
-
Are the permit dates (3 off) correct ? ( check day, month, year)
-
Are the Permit start/end times correct ?
Location Details
-
How accurate is the Plant or Area described for the job concerned ?
-
How accurate is the description of the task ?
-
How detailed / accurate is the Hazard Assessment section completed description ?
-
How detailed / accurate is the "preparations carried out" section completed ?
-
How detailed / accurate is the "Hazard Remaings" section completed ?
-
How detailed / accurate is precautions necessary section completed ?
-
How detailed / accurate is PPE requirements section completed ?
Permit Signatures
-
Are the signatures correct for handover ?
-
Are the hand back signatures left unsigned ?
-
Has the acceptors name and contact details been added ?
Risk Assessment / Method Statement / Isolation Certificate
-
Is a valid Risk Assessment available for the work being carried out ?
-
Is a valid Method Statement available for the work being carried out ?
-
Is an electrical / mechanical isolation certificate in place if required ?
Audit Sign off
-
Auditors Signature
-
Audit Acceptors Signature (eg Contractor)