Information

  • Audit Title

  • Client / Site

  • Conducted on

  • Prepared by

  • Location
  • Personnel

SITE PRESENTATION

  • 1. Site looks presentable on approach?

  • 2. There is BPJV directional signage to the site?

  • 3. The Project Signboard is in place?

  • 4. BPJV sign in place with builders registration no displayed?

  • 5. There are BPJV PPE Signs at each site entry point?

SITE PERIMETER

  • 1. Fence clips are fitted at all panel to panel joints?

  • 2. All site access gates have secure locks and chains?

  • 3. Fence looks visually tidy and in good condition?

SITE COMPOUND

  • 1. The site parking area is well established?

  • 2. The site toilets are clean and well stocked?

  • 3. Crib 1 is clean and well stocked?

  • 4. Crib 2 is clean and well stocked?

  • 5. The Safety Office is clean and tidy?

  • 6. The site first aid point is clearly identified?

  • 7. First aid kit stocked?

  • 8. There is an eyewash station available on site?

  • 9. Site Office 1 is clean and tidy?

  • 10. Site Office 2 is clean and tidy?

SAFETY NOTICES AND POSTERS

  • 1. Up to date BPJV Policies are displayed in crib 1?

  • 2. Up to date BPJV Policies displayed in crib 2?

  • 3. Up to date Site Contacts displayed in crib 1?

  • 4. Up to date Site Contacts displayed in crib 2?

  • 5. Up to date Emergency Plan displayed in crib 1?

  • 6. Up to date Emergency Plan is displayed in crib 2?

SAFETY PROVISIONS

  • 1. There are visitor safety helmets and hi viz available in the safety office?

  • 2. There is spare safety glasses in the safety office?

  • 3. There is spare gloves and glove clips in the safety office?

  • 4. There are ear plugs available in the safety office?

  • 5. There is ample supply of sun protection cream available?

  • 6. There is a supply of bunting available for use by BPJV on site?

  • 7. There is a means of producing required safety signage as required for use by BPJV on site?

  • 8. There are adequate star pickets available for use by BPJV?

TEMPORARY POWER

  • 1. The first main incoming power board is secure?

  • 2. The first incoming power board is tagged in date?

  • 3. The compound temporary power board is secure?

  • 4. The site compound power board is tagged in date?

  • 5. The site compound power board has external isolators for emergency use?

  • 6. The temporary power cabling has "Temporary Power" labelling fitted?

  • 7. The main on site temporary power board is tagged in date?

  • 8. The temporary power cabling is installed safety off the ground as applicable?

  • 9. The temporary site power distribution boards are tagged in date?

  • 10. The power leads into the temporary power boards are safely entering the board?

PLANT PRE-START LOG BOOKS

  • 1. Is the log book filled in today for Generator 1?

  • 2. Is the log book filled in today for Generator 2?

  • 3. Is the log book filled in today for Generator 3?

  • 4. Is the log book filled in today for Generator 4?

  • 5. Is the log book filled in today for Boom lift 1?

  • 6. Is the log book filled in today for Boom lift 2?

  • 7. Is the log book filled in today for Scissor Lift 1?

  • 8. Is the log book filled in today for Scissor Lift 2?

  • 9. Is the log book filled in today for Scissor Lift 3?

  • 10. Is the log book filled in today for Scissor Lift 4?

  • 11. Is the log book filled in today for Scissor Lift 5?

  • 12. Is the log book filled in today for Scissor Lift 6?

  • 13. Is the log book filled in today for Scissor Lift 7?

  • 14. Is the log book filled in today for Scissor Lift 8?

MOBILE PLANT

  • 1. All mobile plant in use on site has operating flashing beacons on?

  • 2. Plant operators have competency tickets?

  • 3. Mobile plant visually inspected appears in good order?

  • 4. Mobile Plant where not in use is secured from unauthorised access?

  • 5. Mobile plant pre-start assessments are being obtained before plant is approved for use on site?

MOBILE SCAFFOLDING

  • 1. Scaffold is erected at suitable height for the activities being carried out?

  • 2. Cross bracing is installed?

  • 3. Diagonal bracing is installed?

  • 4. A suitable platform access ladder is installed?

  • 5. Toe boards are installed?

  • 6. Hand rails and knee rails are installed?

  • 7. Adjustable wheels are installed, adjusted levelling scaffold and locked if in use?

  • 8. If the platform is over 5m then the scaffold has been erected and is tagged by competent scaffolder?

CRANE DOCUMENTATION SETUP & OPERATIONS

  • 1. Crane operation underway on site today?

  • 2. Has the crane documentation been reviewed and approved by The Safety Officer and Site Manager?

  • 3. Has the crane operation JHA been reviewed and approved for the activities being undertaken?

  • 4. Has an acceptable safe work zone been established excluding other workers?

  • 5. Is there adequate crane operation safety signage in place?

  • 6. Does the rigger/s as applicable have suitable competency ticket/s?

  • 7. Are the crane lifting operations being observed being done safely?

ACCESS SCAFFOLDING

  • 1. Is the Admin scaffold tag in date?

  • 2. Is the CB1 scaffold tag in date?

  • 3. Is the CB2 scaffold tag in date?

  • 4. Is the CB3 scaffold tag in date?

  • 5. Is the CB4 scaffold tag in date?

  • 6. Is the CB5 (Alkimos only) scaffold tag in date?

  • 7. Is the Library scaffold tag in date?

  • 8. Is the CAB scaffold tag in date?

  • 9. Is there a means of securing access scaffolds out of hours?

PERMITS SYSTEMS

  • 1. Is the Hot Work permit system being used on site?

  • 2. Is the working at Height Permit system being used on site?

  • 3. Is the Excavation permit system being used on site?

  • 4. Is the confined Space permit system being used on site?

  • 5. Are copies of permits being given to operatives on site?

  • 6. Are permits being filled in correctly?

  • 7. Are works under the permits being done in accordance with the permit? If any observed!

  • 8. Are the permits being closed out properly?

Sign Off

  • 11.2 - Project Managers signature

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.