Title Page
-
Site conducted
-
Site URN
-
Site Address
-
Panel Size
-
Panel Type
-
Installed By:
-
Date(s) of Completion
-
Photo of Completed Panel
QUALITY OF WORKS
-
Have all legacy panels been satisfactorily removed?
-
Have all fixings been removed or made safe?
-
Has any graffiti or obstructions been satisfactorily cleared?
-
Has other wall mounted services and signage been removed or relocated?
-
Is the paintwork on the steelwork completed to a satisfactory standard?
-
Is the fascia / trim aligned and secure?
-
Are the tiles on the screen properly in place and flush with each other?
-
Have the recommended number of pull tests been completed? (Photos MUST be provided)
-
Are there any visible defects with the digital screen or surround?
-
Does the surrounding area detract from the digital screen?
-
Has the trunking been painted if required?
-
Is the height and position of the digital screen(s) correct? (As per planning drawings)
-
Have any remedial works to the wall or substrate been completed as requested?
-
Has the works area been left clean, tidy and in safe condition?
HANDOVER OF DOCUMENTATION AND RECORDS
-
Has the as built drawing been fully annotated? (checked and marked up accordingly with any changes)
-
Have the relevant Site Acceptance Tests (SAT) been completed? (Where applicable)
-
Has the daily signing in and out sheet been returned?
-
Has the signed site induction form been returned?
-
Has the signed RAMS briefing sheet been returned?
-
Has the site based risk assessment been satisfactorily completed?
-
Have all certs, permits and cards been checked to ensure they are valid?
-
Have the signed permit to work forms been returned?
-
Have any plant and equipment check sheets been returned?
-
Have any site briefings or toolbox talks been delivered?
-
Have all photos of the digital screen screen been taken and returned? (Including pods and tiles)
HEALTH AND SAFETY
-
Have the correct chapter 8 barriers / heras fencing panels been used? (Please provide photos)
-
Has the correct signage been used and displayed? (Please provide photos)
-
Has the correct PPE and RPE been worn as per RAMS? (Please provide photos)
-
Have any non-conformances been raised during a site inspection? (Where applicable)
-
Has an IRF been completed for any incidents, near misses or close calls? (Where applicable)
-
Is lifting equipment properly tagged and inspected? (Please state when next LOLER is due)
-
Have safety harnesses and lanyards been inspected and safe to use (Please state date of last inspection)
Completion
-
Site Supervisor (Name):
-
Accepted by (Name):
-
Comments or Actions Required