Title Page

  • Site conducted

  • Site URN

  • Site Address

  • Panel Size

  • Panel Type

  • Installed By:

  • Date of Completion

  • Photo of Completed Panel

QUALITY OF WORKS

  • Have all legacy panels been satisfactorily removed?

  • Have all fixings been removed or made safe?

  • Has any vegetation or waste materials been cleared from site as per Client instructions?

  • Have the foundations been dug to the correct size? (photos of depth and width of foundation)

  • Has the concrete been finished to an acceptable standard?

  • Has shuttering or formwork been removed?

  • Has shuttering or formwork been cut back and left in safe condition?

  • Is the paintwork on the steelwork completed to a satisfactory standard?

  • Is the fascia / trim aligned and secure?

  • Are the tiles on the screen properly in place and flush with each other?

  • Is the plinth the correct size and suitably fitted?

  • Are there any visible defects with the digital screen or surround?

  • Does the surrounding area detract from the digital screen?

  • Is the height and position of the digital screen(s) correct? (As per planning drawings)

  • Has any fencing or ground been re-instated to a satisfactory standard?

  • Has the works area been left clean, tidy and in safe condition?

HANDOVER OF DOCUMENTATION AND RECORDS

  • Has the as built drawing been fully annotated? (checked and marked up accordingly with any changes)

  • Have the relevant Site Acceptance Tests (SAT) been completed? (Where applicable)

  • Has the daily signing in and out sheet been returned?

  • Has the signed site induction form been returned?

  • Has the signed RAMS briefing sheet been returned?

  • Has the site based risk assessment been satisfactorily completed?

  • Have all certs, permits and cards been checked to ensure they are valid?

  • Have the signed permit to work forms been returned?

  • Have any plant and equipment check sheets been returned?

  • Have photos of all vehicles, plant and equipment been taken before and after works?

  • Have photos of all vehicles, plant and equipment been taken before and after works?

  • Have any site briefings or toolbox talks been delivered?

  • Have all photos of the digital screen screen been taken and returned? (Including pods and tiles)

HEALTH AND SAFETY

  • Have the correct chapter 8 barriers / heras fencing panels been used? (Please provide photos)

  • Has the correct signage been used and displayed? (Please provide photos)

  • Has the correct PPE and RPE been worn as per RAMS? (Please provide photos)

  • Have any non-conformances been raised during a site inspection? (Where applicable)

  • Has an IRF been completed for any incidents, near misses or close calls? (Where applicable)

  • Is lifting equipment properly tagged and inspected? (Please state when next LOLER is due)

  • Have safety harnesses and lanyards been inspected and safe to use (Please state date of last inspection)

Completion

  • Site Supervisor (Name):

  • Accepted by (Name):

  • Comments or Actions Required

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.