Site conducted
-
Machine(s) serial number
-
Conducted on
-
Prepared by
undefined
Pre-operation checklist
-
Visually Check condition of power supply plug
-
Visually check hydraulic oil level as above minimum level on tank gauge
-
Visually check hydraulic oil leaks around hoses, cylinders and power pack area
-
Visually check pull down gate mesh is undamaged and still intact
-
Visually check pull down gate handle is intact and door in good order
-
Check operation of pull down gate - ensure gate runs smooth and straight
-
Visually check all guards and covers are undamaged and secure - no missing fasteners
-
Check all safety interlock switches are operational and undamaged
-
Check all emergency stops buttons are operational and undamaged
-
Check all safety switches and push buttons are operational and undamaged
-
Check power supply isolation lock off switch is operational and undamaged
After start-up
-
Check all the safety sensors / interlocks are working as they should
-
Run the baler to ensure the ram moves freely within the machine
Cleaning
-
Between bales - check operation of turnbuckle and thread condition / securing points
-
Between bales - sweep of any waste debris from inside the chamber / behind eject door
-
With power supply padlock isolated, remove waste build up from inside the chamber / behind eject door
-
With power supply padlock isolated, remove large debris from above the compaction blade
-
Remove debris from around the baler:
-
Open panels at back and clean out card debris behind the ram if applicable:
-
Jet wash the baler and around it. (as per site schedule)
At end of shift
-
Do Not attempt any repairs yourself - report to your supervisor / manager
-
Do not attempt to alter any baler settings e.g. pressure switches, limit switches
-
Do Not attempt to override any safety interlock switches or safety guards / covers
-
Do not attempt any cleaning with power supply on - padlock lock off at panel isolator
-
Isolate baler and padlock in place
-
If any faults are found report to helpdesk and put machine out of order
-
I can confirm all checks have been completed
-
List any issues identified during the operation and action taken
-
Operator Name and Signature