Title Page

  • Document No.1

  • B11 WEEKLY PROGRESS REPORT

  • Bath Western Riverside

  • Conducted on

  • Simon Thomas

  • Location
  • Personnel

INTERNAL PROGRESS B1/B2

3003

  • 1st Fix Electrical Complete

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Landscape & Externals Complete

  • Ready for CSI

3004

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Landscape & Externals Complete

  • Ready for CSI

3005

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Landscape & Externals Complete

  • Ready for CSI

3006

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Landscape & Externals Complete

  • Ready for CSI

3011

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Landscape & Externals Complete

  • Ready for CSI

3012

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Landscape & Externals Complete

  • Ready for CSI

3013

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Landscape & Externals Complete

  • Ready for CSI

3014

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Landscape & Externals Complete

  • Ready for CSI

3015

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Landscape & Externals Complete

  • Ready for CSI

3016

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Landscape & Externals Complete

  • Ready for CSI

3017

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Landscape & Externals Complete

  • Ready for CSI

3018

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Landscape & Externals Complete

  • Ready for CSI

3019

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Landscape & Externals Complete

  • Ready for CSI

3020

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Landscape & Externals Complete

  • Ready for CSI

3020

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Landscape & Externals Complete

  • Ready for CSI

3021

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Landscape & Externals Complete

  • Ready for CSI

3022

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Landscape & Externals Complete

  • Ready for CSI

3023

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Landscape & Externals Complete

  • Ready for CSI

3024

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Landscape & Externals Complete

  • Ready for CSI

3025

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Landscape & Externals Complete

  • Crest Site Manager Snagg Complete

  • Ready for CSI

3026

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Landscape & Externals Complete

  • Ready for CSI

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.