Title Page
-
Document No.1
-
B11 WEEKLY PROGRESS REPORT
-
Bath Western Riverside
-
Conducted on
-
Simon Thomas
-
Location
-
Personnel
B6/B12 - EXTERNALS
-
Is the render complete?
-
Is the stone work complete, including copings
-
Are all windows, including curtain walling complete
-
Is the roof complete
-
Have railings been installed
-
Have the Juliet balconies been installed
INTERNAL PROGRESS B6/B12
5007
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
5008
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
5009
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
5010
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
5011
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
5012
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
5013
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
5014
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
5015
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
5016
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
5017
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
5018
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
5019
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
5020
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
5021
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
5022
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
5023
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
5024
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
5025
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
5026
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
5027
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
5028
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
5029
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
5030
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
5031
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
5032
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
5033
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
5034
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
5035
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
5036
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI