Title Page

  • Document No.1

  • B11 WEEKLY PROGRESS REPORT

  • Bath Western Riverside

  • Conducted on

  • Simon Thomas

  • Location
  • Personnel

B11 - EXTERNALS

  • Is the render complete?

  • Is the stone work complete, including copings

  • Are all windows, including curtain walling complete

  • Is the roof complete

  • Have railings been installed

  • Have the Juliet balconies been installed

INTERNAL PROGRESS B11

Communal Ground Floor Core A

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Ready for CSI

6001

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Ready for CSI

6002

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Ready for CSI

6003

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Ready for CSI

6004

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Ready for CSI

6005

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Ready for CSI

Communal 1st Floor Core A

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Ready for CSI

6006

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Ready for CSI

6007

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Ready for CSI

6008

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Ready for CSI

6009

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Ready for CSI

6010

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Ready for CSI

6011

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Ready for CSI

Communal 2nd Floor Core A

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Ready for CSI

6012

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Ready for CSI

6013

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Ready for CSI

6015

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Ready for CSI

6016

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Ready for CSI

6017

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Ready for CSI

Communal 3rd Floor Core A

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Ready for CSI

6018

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Ready for CSI

6019

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Ready for CSI

6020

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Ready for CSI

6021

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Ready for CSI

6022

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Ready for CSI

6023

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Ready for CSI

Communal 4th Floor Core A

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Ready for CSI

6024

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Ready for CSI

6025

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Ready for CSI

6026

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Ready for CSI

6027

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Ready for CSI

6028

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Ready for CSI

Communal 5th Floor Core A

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Ready for CSI

6029

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Ready for CSI

6030

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Ready for CSI

6031

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Ready for CSI

Communal Ground Floor Core B

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Ready for CSI

6032

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Ready for CSI

6033

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Ready for CSI

6034

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Ready for CSI

6035

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Ready for CSI

6036

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Ready for CSI

6036

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Ready for CSI

Communal 1st Floor Core B

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Ready for CSI

6037

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Ready for CSI

6038

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Ready for CSI

6039

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Ready for CSI

6040

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Ready for CSI

6041

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Ready for CSI

Communal 2nd Floor Core B

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Ready for CSI

6042

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Ready for CSI

6043

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Ready for CSI

6044

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Ready for CSI

6045

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Ready for CSI

6046

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Ready for CSI

Communal 3rd Floor Core B

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Ready for CSI

6047

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Ready for CSI

6048

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Ready for CSI

6049

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Ready for CSI

6050

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Ready for CSI

6051

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Ready for CSI

Communal Ground Floor Core C

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Ready for CSI

6052

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Ready for CSI

6053

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Ready for CSI

6054

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Ready for CSI

6055

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Ready for CSI

6056

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Ready for CSI

6057

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Ready for CSI

Communal 1st Floor Core C

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Ready for CSI

6058

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Ready for CSI

6059

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Ready for CSI

6060

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Ready for CSI

6061

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Ready for CSI

6062

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Ready for CSI

6063

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Ready for CSI

6064

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Ready for CSI

Communal 2nd Floor Core C

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Ready for CSI

6065

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Ready for CSI

6067

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Ready for CSI

6068

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Ready for CSI

6069

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Ready for CSI

6070

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Ready for CSI

6071

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Ready for CSI

Communal 3rd Floor Core C

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Ready for CSI

6072

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Ready for CSI

6073

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Ready for CSI

6074

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Ready for CSI

6075

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Ready for CSI

6076

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Ready for CSI

6077

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Ready for CSI

6078

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Ready for CSI

Communal Level 4 Core C

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Ready for CSI

6079

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Ready for CSI

6080

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Ready for CSI

6081

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Ready for CSI

6082

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Ready for CSI

6083

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Ready for CSI

6084

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Ready for CSI

Communal Level 5 Core C

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Ready for CSI

6085

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Ready for CSI

6086

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Ready for CSI

6087

  • 1st Fix Carpentry Complete

  • 1st Fix Plumbing Complete

  • 1st Fix Electrical Complete

  • Wall Insulation Complete along with VCL

  • Boarding Complete

  • Skimming Complete

  • Mist Coat

  • HIU Fitted

  • 2nd Fixed Carpentry Complete

  • 2nd Fix Electrics Complete

  • Wall Tiling Complete

  • Plumbing 2nd Fix Complete

  • Decoration Complete

  • Finals Complete

  • Flooring Complete

  • Plot Clean

  • Crest Site Manager Snagg Complete

  • Ready for CSI

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.