Title Page
-
Document No.1
-
B11 WEEKLY PROGRESS REPORT
-
Bath Western Riverside
-
Conducted on
-
Simon Thomas
-
Location
-
Personnel
B11 - EXTERNALS
-
Is the render complete?
-
Is the stone work complete, including copings
-
Are all windows, including curtain walling complete
-
Is the roof complete
-
Have railings been installed
-
Have the Juliet balconies been installed
INTERNAL PROGRESS B11
Communal Ground Floor Core A
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
6001
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
6002
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
6003
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
6004
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
6005
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
Communal 1st Floor Core A
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
6006
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
6007
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
6008
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
6009
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
6010
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
6011
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
Communal 2nd Floor Core A
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
6012
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
6013
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
6015
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
6016
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
6017
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
Communal 3rd Floor Core A
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
6018
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
6019
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
6020
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
6021
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
6022
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
6023
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
Communal 4th Floor Core A
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
6024
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
6025
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
6026
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
6027
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
6028
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
Communal 5th Floor Core A
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
6029
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
6030
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
6031
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
Communal Ground Floor Core B
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
6032
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
6033
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
6034
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
6035
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
6036
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
6036
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
Communal 1st Floor Core B
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
6037
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
6038
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
6039
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
6040
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
6041
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
Communal 2nd Floor Core B
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
6042
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
6043
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
6044
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
6045
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
6046
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
Communal 3rd Floor Core B
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
6047
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
6048
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
6049
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
6050
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
6051
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
Communal Ground Floor Core C
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
6052
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
6053
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
6054
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
6055
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
6056
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
6057
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
Communal 1st Floor Core C
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
6058
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
6059
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
6060
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
6061
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
6062
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
6063
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
6064
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
Communal 2nd Floor Core C
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
6065
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
6067
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
6068
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
6069
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
6070
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
6071
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
Communal 3rd Floor Core C
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
6072
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
6073
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
6074
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
6075
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
6076
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
6077
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
6078
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
Communal Level 4 Core C
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
6079
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
6080
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
6081
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
6082
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
6083
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
6084
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
Communal Level 5 Core C
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
6085
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
6086
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI
6087
-
1st Fix Carpentry Complete
-
1st Fix Plumbing Complete
-
1st Fix Electrical Complete
-
Wall Insulation Complete along with VCL
-
Boarding Complete
-
Skimming Complete
-
Mist Coat
-
HIU Fitted
-
2nd Fixed Carpentry Complete
-
2nd Fix Electrics Complete
-
Wall Tiling Complete
-
Plumbing 2nd Fix Complete
-
Decoration Complete
-
Finals Complete
-
Flooring Complete
-
Plot Clean
-
Crest Site Manager Snagg Complete
-
Ready for CSI